| 20.5 | B2 WEEKLY PM COMPLETED | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Thu Jan 04 1996 00:36 | 60 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 1/3/96        SYSTEM RTC CODE: CMP.B1     EQUIP. TECH: BJ 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:  100
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   90
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   20
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   26
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   20
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   33
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.8
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   50
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   50
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 10
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   25
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   60
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    X
Comments:  
                                                                        
                                                                       
 | 
| 20.6 | weekly pm ww28 | LUDWIG::RIDLON | Eliminate the obvious | Tue Jan 09 1996 06:32 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 1/9/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: B-shift 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   90
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   60
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   28
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   25
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   20
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   33
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   17
     Note: Sticker on gauge says 17 psi. Which is right?
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   50
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
 
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   25
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   60
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    X
Comments:  
                                                                        
                                                                       
 | 
| 20.8 | Monthly completed. | FABSIX::B_WESTPHAL |  | Sat Jan 20 1996 18:02 | 80 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Monthly Preventative Maintenance Check Sheet, Rev C
 DATE: 1/20/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: D shift
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80 psi
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 52 psi
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 28 psi
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 44 psi
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust: 22 psi
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 psi
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust: 3.2 psi
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust: 25 psi
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 62 psi
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust: 50 psi
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI   Pre-adjust: 25 psi
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 25 psi
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 60 psi
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust: 80 psi
6.1.18 Check system for fluid leaks			Completed:  X
6.1.19 Check tubing/fittings for leaks			Completed:  X
6.1.20 Check system for pneumatic leaks			Completed:  X
6.1.21 Check system indicator lamps			Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4 psi
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:  *N/A
                                                                   
    
6.2.1  Perform Weekly PM Tasks				Completed:   DONE	
6.2.2  Change Peristaltic Pump Lines			Completed:   X
6.2.3  Clean Polish area drain tub			Completed:   X
6.2.4  Check Polish Table Belt for defects		Completed:   X
6.2.5  Check the Neslab water level			Completed:   X
6.2.6  Check the Neslab fittings for leaks              Completed:   X
6.2.7  Check Scrubber Brushes for contaminates/defects	Completed:   X
6.2.8  Check the Load Flipper alignment			Completed:   X
6.2.9  Check the Unload Flipper alignment		Completed:   X
                                                                     
    COMMENTS: * The conditioning arm gimbal bearing was cleaned but not
    lubed.  This is because of a recommendation made by speedfam.  This is
    the completed PM from the previous note.
 | 
| 20.9 | Weekly PM for B2 completed | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Thu Jan 25 1996 05:03 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 1/25/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: BJ 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   80
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   28
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   42
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   50
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   24
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   58
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: Darren asked us not to lubricate the gimbal anymore.... just
          clean it...
                                                                        
                                                                       
 | 
| 20.10 | WW31 Weekly PM | FABSIX::R_POIRIER |  | Wed Jan 31 1996 05:05 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 1/31/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: B Shift 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   52
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   30
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   30
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   58
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 27
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   30
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   60
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: Darren asked us not to lubricate the gimbal anymore.... just
          clean it...
                                                                        
                                                                       
 | 
| 20.12 | ww32 weekly p.m. | FABSIX::R_GEE |  | Mon Feb 05 1996 02:58 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 2/05/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: B Shift 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   30
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   55
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   25
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   58
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: Darren asked us not to lubricate the gimbal anymore.... just
          clean it...
                                                                        
                                                                       
 | 
| 20.13 | Monthly PM for WW33 completed | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Mon Feb 12 1996 17:54 | 25 | 
|  |          SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
              Monthly Preventative Maintenance Check Sheet, Rev C
 DATE: 2/12/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: Doc and BJ
6.2.1  Perform Weekly PM Tasks				Completed:   X	
6.2.2  Change Peristaltic Pump Lines			Completed:   X
6.2.3  Clean Polish area drain tub			Completed:   X
6.2.4  Check Polish Table Belt for defects		Completed:   X
6.2.5  Check the Neslab water level			Completed:   X
6.2.6  Check the Neslab fittings for leaks              Completed:   X
6.2.7  Check Scrubber Brushes for contaminates/defects	Completed:   X
6.2.8  Check the Load Flipper alignment			Completed:   X
6.2.9  Check the Unload Flipper alignment		Completed:   X
Comments:  none
 | 
| 20.14 | weekly ww34 | STRATA::RIDLON | Eliminate the obvious | Mon Feb 19 1996 00:48 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 2/19/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: B Shift
                                                                 w/ M.Andreoli 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   30
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   35
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   55
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   25
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   58
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: Darren asked us not to lubricate the gimbal anymore.... just
          clean it...
                                                                        
 | 
| 20.15 | WW35 Weekly PM | FABSIX::R_POIRIER |  | Mon Feb 26 1996 00:06 | 66 | 
|  | --------------------------------------------------------------------------------
          SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 2/25/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: B Shift
                                                                 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   88
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   25
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   n/a
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   23
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   50
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   45
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: Darren asked us not to lubricate the gimbal anymore.... just
          clean it.
	  Found a water leak in cabinet under Index table. Load cup # 4
          sensor fitting is dripping. Unable to reach in and tighten the
	  fitting.
                                                                        
 | 
| 20.16 | Weekly | SUBPAC::LANDRY |  | Mon Mar 04 1996 19:37 | 60 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 3/4/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: A Shift
                                                                 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   20
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   45
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   50
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   40
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 20
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   45
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments: 
                                                                        
 | 
| 20.17 | semi-a rescheduled | STRATA::TDYER |  | Fri Mar 15 1996 16:10 | 7 | 
|  |     
     The semi-annual PM will be rescheduled. This tool has been in MFG
     for 3.5 months only. Perform and fill out a weekly check sheet for
     this work week.
    
    Tim Dyer
    EEG 
 | 
| 20.18 | Weekly for WW37 completed, Semi-annual waived | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Fri Mar 15 1996 19:22 | 60 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 3/15/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: BJ
                                                                 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   25
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   20
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   45
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   50
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   40
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 20
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   45
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   80
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments:  found DI water in fluids cabinet but source unknown.
                                                                        
 | 
| 20.19 | Weekly PM completed for WW38 | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Fri Mar 22 1996 21:49 | 64 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
    DATE: 3/22/96        SYSTEM RTC CODE: CMP.B2     EQUIP. TECH: BJ
                                                                 
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:   90
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:   85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:   26
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:   40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:   23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:   35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:   30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:   40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:   3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:   25
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:   45
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:   50
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:   60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust: 25
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:   80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:   50
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:   82
6.1.18 Check system for fluid leaks			Completed:    X
6.1.19 Check tubing/fittings for leaks			Completed:    X
6.1.20 Check system for pneumatic leaks			Completed:    X
6.1.21 Check system indicator lamps			Completed:    X
6.1.22 Check stations/components for contamination	Completed:    X
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI  Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:    X
6.1.25 Clean and lubricate the Paddle rails		Completed:    X
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:    N/A
Comments:  found water leaking from chiller line.  Gave alf turn to
           stop but will remove and re-tape if it starts back up.
    
        
                                                                        
        
 | 
| 20.20 | ww 39 B2 weekly completed | FABSIX::B_FINN |  | Sun Mar 24 1996 17:04 | 58 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
 DATE: 3/24/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: A shift
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:82
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:29
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:24
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:24
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust:24
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:50
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:80
6.1.18 Check system for fluid leaks			Completed:done
6.1.19 Check tubing/fittings for leaks			Completed:done
6.1.20 Check system for pneumatic leaks			Completed:done
6.1.21 Check system indicator lamps			Completed:done
6.1.22 Check stations/components for contamination	Completed:done
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI Pre-adjust:5
6.1.24 Clean and lubricate the Scrubber rails		Completed:done
6.1.25 Clean and lubricate the Paddle rails		Completed:done
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed:done
Comments: Adjusted water flow at cassette 2 due to cross slotted wafers
 | 
| 20.21 | Weekly PM started | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Wed Apr 03 1996 05:26 | 58 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
 DATE: 4/3/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: BJ
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:25
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust:27
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:55
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:80
6.1.18 Check system for fluid leaks			Completed:
6.1.19 Check tubing/fittings for leaks			Completed:
6.1.20 Check system for pneumatic leaks			Completed:done
6.1.21 Check system indicator lamps			Completed:done
6.1.22 Check stations/components for contamination	Completed:
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI Pre-adjust:5
6.1.24 Clean and lubricate the Scrubber rails		Completed:done
6.1.25 Clean and lubricate the Paddle rails		Completed:done
6.1.26 Clean and lubricate the Conditioner Gimbal Ass.	Completed: n/a
Comments: chafing neutral wire on vacuum pump
 | 
| 20.22 | Weekly PM completed | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Thu Apr 04 1996 04:21 | 67 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
 DATE: 4/3/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: Brad & BJ
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:25
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust:27
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:55
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:80
6.1.18 Check system for fluid leaks			Completed: done
6.1.19 Check tubing/fittings for leaks			Completed: done
6.1.20 Check system for pneumatic leaks			Completed: done
6.1.21 Check system indicator lamps			Completed: done
6.1.22 Check stations/components for contamination	Completed: done
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI Pre-adjust:5
6.1.24 Clean and lubricate the Scrubber rails		Completed: done
6.1.25 Clean and lubricate the Paddle rails		Completed: done
6.1.26 Clean the Conditioner Gimbal Ass.         	Completed: done
Comments: chafing neutral wire on vacuum pump.  Will repair when tool
          available.
     
          Leak detected in drip pan under the elevators, Reps aware.
          Front right containment pan found full.  Leak detection
          system found off-line.  DI leak appears to be coming from
          scrubber area.  DI picked up and detection system left
          off-line.
 
              
 | 
| 20.23 | Weekly PM for WW41 completed | SUBPAC::BJUBINVILLE | NFD Fire - Rescue | Wed Apr 10 1996 21:45 | 61 | 
|  |           SpeedFam CMP-V Planarizer Maintenance Procedures HF6O-0172
             Weekly Preventative Maintenance Check Sheet, Rev C
 DATE: 4/10/96    SYSTEM RTC CODE: CMP.B2    EQUIP. TECH: BJ
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:40
6.1.5  Check Pad Condition Balance pressure for 23 PSI	Pre-adjust:23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:40
6.1.9  Check Head Balance pressure for 4.2 PSI		Pre-adjust:3.2
6.1.10 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:24
6.1.11 Check Transport Paddle U/D pressure for 45 PSI	Pre-adjust:25
6.1.12 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:60
6.1.13 Check Open Unload Flipper pressure for 45 PSI	Pre-adjust:60
6.1.14 Check Vacuum Tank Blowout pressure for <"<">10 PSI Pre-adjust:27
6.1.15 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:80
6.1.16 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:50
6.1.17 Check MHTA pressure for 60 PSI			Pre-adjust:80
6.1.18 Check system for fluid leaks			Completed: done
6.1.19 Check tubing/fittings for leaks			Completed: done
6.1.20 Check system for pneumatic leaks			Completed: done
6.1.21 Check system indicator lamps			Completed: done
6.1.22 Check stations/components for contamination	Completed: done
6.1.23 Check incoming Chilled Water pressure <"<">10 PSI Pre-adjust:5
6.1.24 Clean and lubricate the Scrubber rails		Completed: done
6.1.25 Clean and lubricate the Paddle rails		Completed: done
6.1.26 Clean the Conditioner Gimbal Ass.         	Completed: done
Comments: Found small puddle of DI in drip pan under the elevators.
          Unknown source and unkown if this was left over from the
          previous fix.
    
 | 
| 20.24 | Weekly PM completed for WW42 | FABSIX::L_SHKOLNIKOV |  | Fri Apr 19 1996 06:57 | 91 | 
|  |     
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI     Pre-adjust: 22
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 22
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  x
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:   Found (3) DI water leaks and (1) chilled water leak
 
                The chiller leak has been corrected
                (1) DI water leak was found in the fluids
                cabinet coming from the bottom section of
                blue solenoids on the right side.  A small
                drip it's there.  Source unknown at this time.
                The other (2) DI leaks are in the front
                containment pan coming from the scrubber area.
                Source unknown at this time.
       ____________________________________________________________
    
 | 
| 20.25 | MONTHLY PM CHECKSHEET   WW43 | ASDG::POIRIER |  | Sat Apr 27 1996 17:35 | 147 | 
|  |                            Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
DATE:  4/27/96      ENTITY: CMP.B1     TECH: C and D shifts
                                               	
6.2.1  Change Peristaltic Pump Lines			Completed:  X
6.2.2  Clean Polish area tub drains			Completed:  X
6.2.3  Check Polish Table Belt for defects		Completed:  X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed:  X
       Down Frc: Head 1 Pre-Adj: 382.3    Post-adj: 377.8
                 Head 2 Pre-Adj: 372.6    Post-adj: 374.8
                 Head 3 Pre-Adj: 390.8    Post-adj: 374.6
                 Head 4 Pre-Adj: 377.7    Post-adj: 377.7
                 Head 5 Pre-Adj: 392.2    Post-adj: 374.8
6.2.5  Perform Down Force Calibration on Conditioner    Completed:   X
       Actual Down Force Pre-Adj:  76.6
       Actual Down Force Post-Adj: 76.6                    
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:   X
6.2.7  Check the Load Flipper alignment			Completed:   X
6.2.8  Check the Unload Flipper alignment		Completed:   X
6.2.9  Check the Elevator alignment                     Completed:   X
6.2.10 Check wafer unload, from Index table to cassette Completed:   X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: 23.92V
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: 15.08V
6.2.13 Check the +5 Volt power supply                   Pre-Adjust:  4.97V
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed:   X 31 RPM
6.2.15 Check Vacuum Pump Diaphrams			Completed:   X
6.2.16 Check Vacuum Tank/Pump lines			Completed:   X
6.2.17 Check Load Cup Position alignments		Completed:   X
6.2.18 Check Load Cup Height alignments                 Completed:   X 
6.2.19 Check Robot alignments			        Completed:   X
6.2.20 Check Muffin Fans for proper operation           Completed:   X
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:  85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:  80
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:  28
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:  40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust:  23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:  35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:  30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:  40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust:  3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust:  20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:  20
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust:  20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:  60
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust:  60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust:  25
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:  80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:  50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust:  80
6.1.19 Check Drip Pan for moisture/contamination        Completed:   X
6.1.20 Check tubing/fittings for fluid leaks            Completed:   X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:   X
6.1.22 Check stations/components for contamination	Completed:   X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust:  4
6.1.24 Clean and lubricate the Scrubber rails		Completed:   X
6.1.25 Clean and lubricate the Paddle rails		Completed:   X
6.1.26 Clean Conditioning Wheel and Housing             Completed:   X
6.1.27 Scrub clean the Polish area tub and walls        Completed:   X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:   X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:   X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:   X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:   X
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:   X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed    X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:   X
6.1.35 Clean the slurry delivery tube                   Completed:   X
6.1.36 Check chiller fluid resevoir for proper level    Completed:   X
Comments:   Small DI leak found in fluid cabinet.  Looks like it is
            coming from the lower right side of the DI manifold.
    
            Another small puddle of DI was found in front of tool
            under scrubber.  After a week, a puddle about 2" in
            diameter was found.
 | 
| 20.26 | Weekly PM completed for WW44 | SUBPAC::BJUBINVILLE | CMP Equipment Engineering | Wed May 01 1996 23:11 | 84 | 
|  |     
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 5/1/96   TOOL: CMP.B2   TECH/SHIFT: D shift 
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI     Pre-adjust: 24
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 22
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 84
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  n/a
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:   Found DI water 3" spot under scrubber.  Will look into 
            source later this week when tool free.
    
   
 | 
| 20.27 | WEEKLY PM FOR WW45 COMPLETED | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Thu May 09 1996 22:53 | 79 | 
|  |                            Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 5/8/96   TOOL: CMP.B2   TECH/SHIFT: C and D
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 26
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
                                                                     
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 20
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  n/a
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:  
 | 
| 20.28 | CMP.B2 MONTHLY PM FOR WW46 COMPLETED | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Thu May 16 1996 21:15 | 145 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
DATE: 5/16/96        TOOL: CMP.B2              TECH/SHIFT: D & C
6.2.1  Change Peristaltic Pump Lines			Completed: X
6.2.2  Clean Polish area tub drains			Completed: X
6.2.3  Check Polish Table Belt for defects		Completed: X 
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: X
       Down Frc: Head 1 Pre-Adj: 367   Post-adj: 377 
                 Head 2 Pre-Adj: 375   Post-adj: 377 
                 Head 3 Pre-Adj: 358   Post-adj: 377 
                 Head 4 Pre-Adj: 370   Post-adj: 377 
                 Head 5 Pre-Adj: 373   Post-adj: 377 
6.2.5  Perform Down Force Calibration on Conditioner    Completed: X
       Actual Down Force Pre-Adj: 46 @ 67%
       Actual Down Force Post-Adj: N/A
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: X
6.2.7  Check the Load Flipper alignment			Completed: x
6.2.8  Check the Unload Flipper alignment		Completed: x
6.2.9  Check the Elevator alignment                     Completed: X
6.2.10 Check wafer unload, from Index table to cassette Completed:  X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: X 
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: X
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: X
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed:  X
6.2.15 Check Vacuum Pump Diaphrams			Completed:  X
6.2.16 Check Vacuum Tank/Pump lines			Completed:  X
 
6.2.17 Check Load Cup Position alignment		Completed:  X
6.2.18 Check All Load Cup Height alignments             Completed:  X
6.2.19 Check Robot alignments			        Completed:  X
6.2.20 Check Muffin Fans for proper operation           Completed: X
Comments:
                                                                    
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 83
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 24
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 45
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23.5
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 30
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 24  POST 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30 New  
                                                                       Value
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
               
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments: The "Vacuum Tank Blowout Pressure" has been increased to
          30 psi as of 5/16/96.
                                                                   
    
 | 
| 20.29 | WW47 WEEKLY PM | FABSIX::L_SHKOLNIKOV |  | Fri May 24 1996 04:12 | 82 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 5/22-24/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 90
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 24
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 18
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
                                                                   
    
 | 
| 20.30 | SHUTDOWN CHECKSHEET | STRATA::RIDLON | Eliminate the obvious | Mon May 27 1996 06:36 | 25 | 
|  | 
                        CMP.B SHUT DOWN CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
								 INIT / DATE
1) SCRUB SIDES OF CARRIERS					___B__/5/27__
2) RUN CARRIER BLOW OFF FOR 30 SECONDS				___B__/______
3) REMOVE ALL CARRIERS						___B__/______
4) PLACE WIPES UNDER CARRIER FILMS AND LAY CARRIERS DI TANK	___B__/______
5) IF POWER TO SLURRY SYSTEM IS GOING TO BE LOST, CONTACT 
   ASHLAND CHEMICAL AND HAVE SLURRY SYSTEM PURGED AND CHARGED 
   WITH DI WATER.						___B__/______
6) CLEAN ENTIRE SYSTEM OF DRIED SLURRY 			        ___B__/______
7) REMOVE CONDITIONER AND CLEAN					___B__/______
8) CYCLE/RINSE ALL DI FUNCTIONS: SPRAY NOZZLES, SLURRY PUMPS,
   CONDITIONER RINSE, ELEVATOR TANKS.				___B__/______
9) SHUT OFF DI BEHIND SYSTEM (ROTATE 3W VLV TO FULL RETURN)     ___B__/______ 
10) DRAIN ELEVATOR AND CONDITIONER TUBE				___B__/______
11) REMOVE PADS, AND CLEAN AND DRY TABLES			___B__/______
12) REMOVE SCRUBBER BRUSHES AND SOAK IN DI			___B__/______
13) DRY ENTIRE SYSTEM OF ANY STANDING WATER			___B__/______
14) POWER DOWN SYSTEM.
 | 
| 20.31 | Weekly PM performed | SUBPAC::LANDRY |  | Tue May 28 1996 18:42 | 82 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 5/28/96        TOOL: CMP.B2              TECH/SHIFT: A & B shifts
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 90
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 22
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.4
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
                                                                   
    
 | 
| 20.32 | Startup Checksheet | SUBPAC::LANDRY |  | Tue May 28 1996 19:01 | 19 | 
|  | 
                        CMP.B START UP CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
                                                                 INIT / DATE
1) TURN ON DI WATER (ROTATE 3W VLV TO FULLY TO POLISHER.        A shift  5/28
2) POWER ON SYSTEM.						A shift  5/28
3) CYCLE/RUN ALL DI FUNCTIONS FOR 15 MINUTES			A shift  5/28
4) WIPE DOWN SYSTEM CLEAN ALL DRIED SLURRY	                A shift  5/28
5) DRY TABLES, INSTALL PADS					A shift  5/28
6) INSTALL SCRUBBER BRUSHES					A shift  5/28
7) INSTALL CONDITIONER						A shift  5/28
8) INSTALL CARRIERS						A shift  5/28
9) RUN WET IDLE PROGRAM FOR 15 MIN. (ENOUGH TO CLEAN CARRIERS)  A shift  5/28
10) IF SLURRY SYSTEM WAS SHUT DOWN, CONTACT ASHLAND CHEMICAL,
    REQUEST DI TO BE PURGE FROM SLURRY SYSTEM AND CHARGED WITH 
    SLURRY AND REQUEST A NEW SLURRY FILTER BE INSTALLED.	    N/A
11) CALIBRATE SLURRY FLOW					A shift  5/28
12) PUT IN WET IDLE AND TURN OVER TO MFG FOR MQC		A shift  5/28
 | 
| 20.33 | MONTHLY P.M. COMPLETED FOR WW 49 | FABSIX::J_SWENSON |  | Sat Jun 08 1996 14:56 | 174 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
DATE 7/6/96            ENTITY CMP.B2           TECH/SHIFT:  D-shift 
6.2.1  Change Peristaltic Pump Lines			Completed: X
6.2.2  Clean Polish area tub drains			Completed: X
6.2.3  Check Polish Table Belt for defects		Completed: X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: X
       Down Frc: Head 1 Pre-Adj:______ Post-adj:______   " SEE COMMENTS"
                 Head 2 Pre-Adj:______ Post-adj:______
                 Head 3 Pre-Adj:______ Post-adj:______
                 Head 4 Pre-Adj:______ Post-adj:______
                 Head 5 Pre-Adj:______ Post-adj:______
6.2.5  Perform Down Force Calibration on Conditioner    Completed: x
       Actual Down Force Pre-Adj:_____________50.1 @67%
       Actual Down Force Post-Adj:____________
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: X
6.2.7  Check the Load Flipper alignment			Completed: X
6.2.8  Check the Unload Flipper alignment		Completed: X
6.2.9  Check the Elevator alignment                     Completed: X
6.2.10 Check wafer unload, from Index table to cassette Completed: X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust:  23.96
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust:+15.06/-15.09
6.2.13 Check the +5 Volt power supply                   Pre-Adjust:  4.97
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: X 
6.2.15 Check Vacuum Pump Diaphrams			Completed: X
6.2.16 Check Vacuum Tank/Pump lines			Completed: X
6.2.17 Check Load Cup Position alignment		Completed: X
6.2.18 Check Load Cup Height alignment                  Completed: X
6.2.19 Check Robot alignments			        Completed: X
6.2.20 Check Muffin Fans for proper operation           Completed: X
Comments:
    
--------------------------------------------------------------------------------
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 45
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 24
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 30
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X***
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 5.5 psi
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
                                                        
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X   
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:These are the values for the 5 carrier heads during the down
         force check. (NO ADJUSTMENTS WERE MADE, TOOL WAS RUNNING FINE WITH
                       CURRENT OFFSETS)
                      [ STATUS          SCREEN  ]
CARRIER #            PROGRAMMED            ACTUAL              SENSOTEC LOAD
   1                    377                 375                    377.5
   2                    377                 376                    423.5
   3                    377                 374                    374.5
   4                    377                 379                    342
  
   5                    377                 379                    381.6
  ***   Head # 2 would ramp to around 275 then have about a ten sec. delay 
  ***   and ramp up to the 400 range on the sensotec load.
  * found small droplets of DI on bottom of fluids cabinet, manufacturing
    needed the tool so returned for production use. This will need to be looked
    at before becoming worse.
                                     C SHIFT
 | 
| 20.34 | Weekly PM for WW50 completed | FABSIX::L_SHKOLNIKOV |  | Tue Jun 11 1996 23:29 | 82 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 6/11/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 25
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: n/a
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3.0
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
                                                                   
    
 | 
| 20.35 | Weekly PM for WW51 completed | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Thu Jun 20 1996 04:39 | 83 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 6/20/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 22
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: n/a
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3.5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
                                                                   
    
                                                                     
 | 
| 20.36 | weekly PM for WW52 completed | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Tue Jun 25 1996 22:47 | 84 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 6/25/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 24
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
                                                                   
    
                                                                     
                                                                     
 | 
| 20.37 | B2 weekly PM completed for WW1 | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Thu Jul 04 1996 01:49 | 89 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 7/3/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 22
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 3
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:    slurry detection system off-line until after shut-down.
    
             The black wire in currently disconnected which deactivates
             the detector and tricks the tool.
    
             The black wire goes in the middle screw opening.
                                                                   
    
                                                                     
                                                                     
 | 
| 20.39 | B2 SHUT-DOWN COMPLETED | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Thu Jul 04 1996 01:55 | 26 | 
|  | 
                        CMP.B2 SHUT DOWN CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
							        SHIFT / DATE
1) SCRUB SIDES OF CARRIERS					  D    7/3/96
2) RUN CARRIER BLOW OFF FOR 30 SECONDS				  D    7/3/96
3) REMOVE ALL CARRIERS						  D    7/3/96
4) PLACE WIPES UNDER CARRIER FILMS AND LAY CARRIERS DI TANK	  D    7/3/96
5) IF POWER TO SLURRY SYSTEM IS GOING TO BE LOST, CONTACT 
   ASHLAND CHEMICAL AND HAVE SLURRY SYSTEM PURGED AND CHARGED 
   WITH DI WATER.						  D    7/3/96
6) CLEAN ENTIRE SYSTEM OF DRIED SLURRY 			          D    7/3/96
7) REMOVE CONDITIONER AND CLEAN					  D    7/3/96
8) CYCLE/RINSE ALL DI FUNCTIONS: SPRAY NOZZLES, SLURRY PUMPS,
   CONDITIONER RINSE, ELEVATOR TANKS.			          D    7/3/96
9) SHUT OFF DI BEHIND SYSTEM (ROTATE 3W VLV TO FULL RETURN)       D    7/3/96 
10) DRAIN ELEVATOR AND CONDITIONER TUBE				  D    7/3/96
11) REMOVE PADS, AND CLEAN AND DRY TABLES	        	  D    7/3/96
12) REMOVE SCRUBBER BRUSHES AND SOAK IN DI			  D    7/3/96
13) DRY ENTIRE SYSTEM OF ANY STANDING WATER			  D    7/3/96
14) POWER DOWN SYSTEM.                                            D    7/3/96
    
    
                              
 | 
| 20.40 | B1 Startup completed | FABSIX::L_SHKOLNIKOV |  | Sat Jul 06 1996 03:33 | 21 | 
|  | 
                        CMP.B2 START UP CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
                                                                 INIT / DATE
1) TURN ON DI WATER (ROTATE 3W VLV TO FULLY TO POLISHER.	__LS__/7-6-96
2) POWER ON SYSTEM.						__LS__/7-6-96
3) CYCLE/RUN ALL DI FUNCTIONS FOR 15 MINUTES			__LS__/7-6-96
4) WIPE DOWN SYSTEM CLEAN ALL DRIED SLURRY	                __LS__/7-6-96
5) DRY TABLES, INSTALL PADS					__LS__/7-6-96
6) INSTALL SCRUBBER BRUSHES					__LS__/7-6-96
7) INSTALL CONDITIONER						__LS__/7-6-96
8) INSTALL CARRIERS						__LS__/7-6-96
9) RUN WET IDLE PROGRAM FOR 15 MIN. (ENOUGH TO CLEAN CARRIERS)  __LS__/7-6-96
10) IF SLURRY SYSTEM WAS SHUT DOWN, CONTACT ASHLAND CHEMICAL,
    REQUEST DI TO BE PURGE FROM SLURRY SYSTEM AND CHARGED WITH 
    SLURRY AND REQUEST A NEW SLURRY FILTER BE INSTALLED.	__LS__/7-6-96
11) CALIBRATE SLURRY FLOW					__LS__/7-6-96
12) PUT IN WET IDLE AND TURN OVER TO MFG FOR MQC		__LS__/7-6-96
 | 
| 20.41 | ww2 monthly p.m. completed | FABSIX::J_SWENSON |  | Fri Jul 12 1996 11:49 | 147 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
DATE: 7/12/96        TOOL: CMP.B2              TECH/SHIFT: BJ,JP,JS&BW.
                                                           D & C SHIFTS.
6.2.1  Change Peristaltic Pump Lines			Completed:  X
                                   
6.2.2  Clean Polish area tub drains			Completed:  X
6.2.3  Check Polish Table Belt for defects		Completed:  X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed:  X
       Down Frc: Head 1 Pre-Adj: 371   Post-adj: 377
                 Head 2 Pre-Adj: 361   Post-adj: 377
                 Head 3 Pre-Adj: 383   Post-adj: 376
                 Head 4 Pre-Adj: 360   Post-adj: 375
                 Head 5 Pre-Adj: 373   Post-adj: n/c
6.2.5  Perform Down Force Calibration on Conditioner    Completed:  X
       Actual Down Force Pre-Adj:___77.1__________
       Actual Down Force Post-Adj:__n/c__________
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:  BJ
6.2.7  Check the Load Flipper alignment			Completed:  BJ
6.2.8  Check the Unload Flipper alignment		Completed:  BJ
6.2.9  Check the Elevator alignment                     Completed:  BJ
6.2.10 Check wafer unload, from Index table to cassette Completed:  X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: 23.6 v
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: 15.04 v
6.2.13 Check the +5 Volt power supply                   Pre-Adjust:  4.96 v
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed:   31.6 rpm
6.2.15 Check Vacuum Pump Diaphrams			Completed:  X
6.2.16 Check Vacuum Tank/Pump lines			Completed:  X
6.2.17 Check Load Cup Position alignment		Completed:  X
6.2.18 Check Load Cup Height alignment                  Completed:  X
6.2.19 Check Robot alignments			        Completed:  BJ
6.2.20 Check Muffin Fans for proper operation           Completed:  X
Comments:
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 7/12/96        TOOL: CMP.B2              TECH/SHIFT: BJ,JP,JS & BW.
                                                           D & C Shifts.
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 24
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:   X
6.1.20 Check tubing/fittings for fluid leaks            Completed:   X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:   X
6.1.22 Check stations/components for contamination	Completed:   X 
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  BJ
6.1.25 Clean and lubricate the Paddle rails		Completed:  BJ
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  BJ
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  BJ
Comments:    Found DI water on bottom of tool. Wiped up and will
             monitor to determine leak origin.
 | 
| 20.42 | ww3 weekly pm | FABSIX::L_SHKOLNIKOV |  | Sat Jul 20 1996 07:34 | 79 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 7/20/96        TOOL: CMP.B2              TECH/SHIFT: D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 28
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.6
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments: 
 | 
| 20.43 | WW IV - Weekly | SUBPAC::LANDRY |  | Tue Jul 23 1996 18:16 | 82 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 7/23/96        TOOL: CMP.B2              TECH/SHIFT: A shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 26
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.4
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:  Found excessive amount of slurry on the underside of the MHTA,
           in the vacinity on the delivery tube entrance.
           Pad and all carriers were changed out at this time due to high
           particles and carriers drying out during idle time.
 | 
| 20.44 | WW05 WEEKLY PM | FABSIX::L_SHKOLNIKOV |  | Sat Aug 03 1996 00:01 | 78 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 8/02/96        TOOL: CMP.B2              TECH/SHIFT: C+D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 82
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 20
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.4
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments: 
 | 
| 20.45 | Monthly moved | STRATA::TDYER |  | Fri Aug 09 1996 18:26 | 6 | 
|  |     
     The monthly PM is being moved to next week, perform weekly in place.
    
    Tim Dyer
    EEG
                                           
 | 
| 20.46 | WW06 WEEKLY P.M. | FABSIX::J_SWENSON |  | Sat Aug 10 1996 15:59 | 80 | 
|  | 
                           Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 8/10/96        TOOL: CMP.B2              TECH/SHIFT: C/D SHIFT      
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 83   
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 20  
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 39
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23.5 
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35    
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30.5  
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2   
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A  
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50  
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 52
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 19     
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 52  
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 2.4
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X 
Comments: 
 | 
| 20.47 | WW7 MONTHLY P.M. DEFERRED TO WW8 | ASDG::POIRIER |  | Sat Aug 17 1996 18:59 | 6 | 
|  |     
    WW7 MONTHLY & WEEKLY P.M.'S ARE BEING DEFERRED PER JOHN HOEKSTRA DUE
    TO EQUIPMENT AVAILABILITY. BOTH PARTIALLY COMPLETED CHECKSHEETS
    HAVE BEEN POSTED IN NOTE #60. (INCOMPLETE P.M. CHECKSHEETS)
    
                                                              C SHIFT. 
 | 
| 20.48 | Monthly p.m. completed | FABSIX::R_GEE |  | Sat Aug 17 1996 22:45 | 150 | 
|  | 
    
                            WW7 MONTHLY PM CHECKSHEET
    
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
                                           	
6.2.1  Change Peristaltic Pump Lines			Completed: X
6.2.2  Clean Polish area tub drains			Completed: X
6.2.3  Check Polish Table Belt for defects		Completed: X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: X
       Down Frc: Head 1 Pre-Adj:_380__ Post-adj:_377_+/-1 %_
                 Head 2 Pre-Adj:_362__ Post-adj:_377_+/-1 %
                 Head 3 Pre-Adj:_354__ Post-adj:_377_+/-1 %
                 Head 4 Pre-Adj:_380__ Post-adj:_377 +/-1 %
                 Head 5 Pre-Adj:_340__ Post-adj:_377 +/-1 %
6.2.5  Perform Down Force Calibration on Conditioner    Completed:
       Actual Down Force Pre-Adj:___83_______
       Actual Down Force Post-Adj:__77 +/-1 %
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:  X
6.2.7  Check the Load Flipper alignment			Completed:  X
6.2.8  Check the Unload Flipper alignment		Completed:  X
6.2.9  Check the Elevator alignment                     Completed:  X
6.2.10 Check wafer unload, from Index table to cassette Completed:  X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: 22.94 VDC
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: 15.04 VDC
6.2.13 Check the +5 Volt power supply                   Pre-Adjust:  4.96 VDC
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: X
6.2.15 Check Vacuum Pump Diaphrams			Completed:  N/A
6.2.16 Check Vacuum Tank/Pump lines			Completed:  X
6.2.17 Check Load Cup Position alignment		Completed:  X
6.2.18 Check Load Cup Height alignment                  Completed:  X
6.2.19 Check Robot alignments			        Completed:  X
6.2.20 Check Muffin Fans for proper operation           Completed:  X
Comments:
    
--------------------------------------------------------------------------------
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 81 PSI
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 26
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust:  3
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: 20
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 26
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 82
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X 
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 4 PSI
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed:  X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
 | 
| 20.49 | ww08 weekly pm | FABSIX::L_SHKOLNIKOV |  | Thu Aug 22 1996 05:19 | 79 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 8/22/96        TOOL: CMP.B2              TECH/SHIFT:   D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 86
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 28   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  x
6.1.20 Check tubing/fittings for fluid leaks            Completed:  x
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  x
6.1.22 Check stations/components for contamination	Completed:  x
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8 
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  x
6.1.26 Clean Conditioning Wheel and Housing             Completed:  x
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  x
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  x
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  x
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  x
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   x
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  x
6.1.35 Clean the slurry delivery tube                   Completed:  x
6.1.36 Check chiller fluid resevoir for proper level    Completed:  x
Comments: Found small puddle of DI in drip pan under the scrubber drain.
          Wiped it out and put some silicone seal over the drain.
 | 
| 20.50 | CMP.B2 SHUTDOWN CHECKSHEET | FABSIX::R_POIRIER |  | Mon Sep 02 1996 01:51 | 30 | 
|  | 
                        CMP.B2 SHUT DOWN CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
							        SHIFT / DATE
1) SCRUB SIDES OF CARRIERS					  B    9-1-96
2) RUN CARRIER BLOW OFF FOR 30 SECONDS				  B    9-1-96
3) REMOVE ALL CARRIERS						  B    9-1-96
4) PLACE WIPES UNDER CARRIER FILMS AND LAY CARRIERS DI TANK	  B    9-1-96
5) IF POWER TO SLURRY SYSTEM IS GOING TO BE LOST, CONTACT 
   ASHLAND CHEMICAL AND HAVE SLURRY SYSTEM PURGED AND CHARGED 
   WITH DI WATER.						  B    9-1-96
6) CLEAN ENTIRE SYSTEM OF DRIED SLURRY 			          B    9-1-96
7) REMOVE CONDITIONER AND CLEAN					  B    9-1-96
8) CYCLE/RINSE ALL DI FUNCTIONS: SPRAY NOZZLES, SLURRY PUMPS,
   CONDITIONER RINSE, ELEVATOR TANKS.			          B    9-1-96
9) JUMPER DI PRESSURES SWITCHES                                   B    9-1-96
10) SHUT OFF DI BEHIND SYSTEM (ROTATE 3W VLV TO FULL RETURN)      B    9-1-96 
11) DRAIN ELEVATOR AND CONDITIONER TUBE				  B    9-1-96
12) REMOVE PADS, AND CLEAN AND DRY TABLES	        	  B    9-1-96
13) REMOVE SCRUBBER BRUSHES AND SOAK IN DI			  B    9-1-96
14) DRY ENTIRE SYSTEM OF ANY STANDING WATER			  B    9-1-96
15) TURN OFF CHILLER					          B    9-1-96
  ** DO NOT TURN POWER OFF TO POLISHER **
  ** THE MAIN PCW VALES ARE TO BE SHUT IN THE PIPE GALLERY  **
    
    
                              
 | 
| 20.51 | semiannual completed on time but check sheet late | STRATA::WESTPHAL |  | Tue Sep 03 1996 17:34 | 171 | 
|  | 
    
                           Speedfam Corp. CMP-V Planarizer
             Semi-Annual Preventative Maintenance Check Sheet, Rev D
    
             Date 8/31/96                       Techs: c/b shift            
    
6.4.1  Check all interlocks for functionality		Completed: X
6.4.2  Check all EMO's for functionality		Completed: X
6.4.3  Lubricate the Rotary Union			Completed: * note
6.4.4  Lubricate the Lead Screw				Completed: X
6.4.5  Lubricate the Linear Guide Rails			Completed: X
6.4.6  Lubricate the Idler Pulley			Completed: X
Comments:
--------------------------------------------------------------------------------
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
                                           	
6.2.1  Change Peristaltic Pump Lines			Completed:  X
6.2.2  Clean Polish area tub drains			Completed:  X
6.2.3  Check Polish Table Belt for defects		Completed:  X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed:  X
       Down Frc: Head 1 Pre-Adj: 376.8  Post-adj: N/A
                 Head 2 Pre-Adj: 399.8  Post-adj: 378.8
                 Head 3 Pre-Adj: 377.7  Post-adj: N/A
                 Head 4 Pre-Adj: 376.2  Post-adj: N/A
                 Head 5 Pre-Adj: 397.6  Post-adj: 377.4
6.2.5  Perform Down Force Calibration on Conditioner    Completed:  X
       Actual Down Force Pre-Adj:  86.7 LBS
       Actual Down Force Post-Adj: 78.0 LBS
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:  X
6.2.7  Check the Load Flipper alignment			Completed:  X
6.2.8  Check the Unload Flipper alignment		Completed:  X
6.2.9  Check the Elevator alignment                     Completed:  X
6.2.10 Check wafer unload, from Index table to cassette Completed:  X
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: 23.06 V
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: 15.04 V
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: 4.96  V
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: 30.3 RPM
6.2.15 Check Vacuum Pump Diaphrams			Completed:  N/A
6.2.16 Check Vacuum Tank/Pump lines			Completed:  X
6.2.17 Check Load Cup Position alignment		Completed:  X
6.2.18 Check Load Cup Height alignment                  Completed:  X
6.2.19 Check Robot alignments			        Completed: X
6.2.20 Check Muffin Fans for proper operation           Completed: X
Comments:
--------------------------------------------------------------------------------
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 84
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 80
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 18
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 50
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 4
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments:
           * Note - Waiting for the correct lubricant then item will be 
completed ASAP.
 | 
| 20.52 | WW X - completed | SUBPAC::LANDRY |  | Sun Sep 08 1996 10:43 | 78 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 9/07-08/96        TOOL: CMP.B2           TECH/SHIFT:   D + A shifts
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 86
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  X
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  X
6.1.22 Check stations/components for contamination	Completed:  X
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 10
6.1.24 Clean and lubricate the Scrubber rails		Completed:  X
6.1.25 Clean and lubricate the Paddle rails		Completed:  X
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  X
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed:  X
Comments: 
 | 
| 20.53 | ww11 weekly pm | FABSIX::L_SHKOLNIKOV |  | Fri Sep 13 1996 04:39 | 80 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 9/13/96        TOOL: CMP.B2           TECH/SHIFT:   D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 25
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 25   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  x
6.1.20 Check tubing/fittings for fluid leaks            Completed:  x
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  x
6.1.22 Check stations/components for contamination	Completed:  x
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  x
6.1.26 Clean Conditioning Wheel and Housing             Completed:  x
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  x
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  x
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  x
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  n/a
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  x
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   x
6.1.34 Wipe the Process Area Plexiglas doors w/Iso      Completed:  x
6.1.35 Clean the slurry delivery tube                   Completed:  n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed:  x
Comments:   The polish area drain pipe which located between index and 
            main polish table seems to be clogged - it drains the water 
            very slow. Will check it again in couple days.
 | 
| 20.54 | Weekly PM completed for WW12 | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Tue Sep 17 1996 22:45 | 78 | 
|  |                            Speedfam Corp. CMP-V Planarizer          
                Weekly Preventative Maintenance Check Sheet, Rev D
    
DATE: 9/17/96        TOOL: CMP.B2           TECH/SHIFT:   D shift
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 22
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35  
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 26   
                                                                       
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 52
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 82
6.1.19 Check Drip Pan for moisture/contamination        Completed:  x
6.1.20 Check tubing/fittings for fluid leaks            Completed:  x
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  x
6.1.22 Check stations/components for contamination	Completed:  x
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  x
6.1.26 Clean Conditioning Wheel and Housing             Completed:  x
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  x
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  x
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  x
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  n/a
                      - the liquid seperator                        x
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  x
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   x
6.1.34 Wipe the Process Area Plexiglas doors w/Iso      Completed:  x
6.1.35 Clean the slurry delivery tube                   Completed:  n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed:  x
Comments:  
 | 
| 20.55 | WEEKLY PM FOR WW13 COMPLETED | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Fri Sep 27 1996 19:34 | 84 | 
|  |           SPEC# HF60-0172  REV-D   SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
      
                        Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 9-27-96             TOOL: CMP.B2               TECH/SHIFT: D shift
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 24
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 22
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 18
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  x
6.1.20 Check tubing/fittings for fluid leaks            Completed:  x
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  x
6.1.22 Check stations/components for contamination	Completed:  x
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  x
6.1.26 Clean Conditioning Wheel and Housing             Completed:  x
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  x
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  x
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  x
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  n/a
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  x
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   x
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  x
6.1.35 Clean the slurry delivery tube                   Completed:  x
6.1.36 Check chiller fluid resevoir for proper level    Completed:  x
Comments:
       ____________________________________________________________
    
 | 
| 20.56 | WEEKLY COMPLETED WW#14 | STRATA::WESTPHAL |  | Sat Oct 05 1996 10:29 | 85 | 
|  | --------------------------------------------------------------------------------
    
          SPEC# HF60-0172  REV-D   SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
      
                        Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 10/4/96             TOOL: CMP.B2               TECH/SHIFT: D shift
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 22
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination        Completed:  x
6.1.20 Check tubing/fittings for fluid leaks            Completed:  x
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  x
6.1.22 Check stations/components for contamination	Completed:  x
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8
6.1.24 Clean and lubricate the Scrubber rails		Completed:  x
6.1.25 Clean and lubricate the Paddle rails		Completed:  x
6.1.26 Clean Conditioning Wheel and Housing             Completed:  x
6.1.27 Scrub clean the Polish area tub and walls        Completed:  x
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  x
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  x
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  x
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  x
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  x
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   x
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  x
6.1.35 Clean the slurry delivery tube                   Completed:  n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed:  x
Comments:   6.1.28 completed while 2nd table pad was changed at
            beginning of shift
                              
 | 
| 20.57 | MONTHLY PM COMPLETED FOR WW15 | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Tue Oct 15 1996 19:33 | 155 | 
|  | 
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
                                           	        Techs/c/d Shift
6.2.1  Change Peristaltic Pump Lines			Completed:  X
6.2.2  Clean Polish area tub drains			Completed:  X
6.2.3  Check Polish Table Belt for defects		Completed:  X
6.2.4  Perform Down Force Calibration on all 5 heads    Completed:  D-SHIFT 
       Down Frc: Head 1 Pre-Adj: 375LBS Post-adj: DID NOT CHANGE
                 Head 2 Pre-Adj: 384LBS Post-adj: 377LBS
                 Head 3 Pre-Adj: 377LBS Post-adj: DID NOT CHANGE
                 Head 4 Pre-Adj: 387LBS Post-adj: 376LBS
                 Head 5 Pre-Adj: 378LBS Post-adj: DID NOT CHANGE
6.2.5  Perform Down Force Calibration on Conditioner    Completed: D-SHIFT 
       Actual Down Force Pre-Adj: 73LBS @ 100%  55LBS @ 67%
       Actual Down Force Post-Adj:____________
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:  X
6.2.7  Check the Load Flipper alignment			Completed:  BJ
6.2.8  Check the Unload Flipper alignment		Completed:  BJ
6.2.9  Check the Elevator alignment                     Completed:  BJ
6.2.10 Check wafer unload, from Index table to cassette Completed:  BJ
6.2.11 Check the +24 Volt power supply                  Pre-Adjust: 24.01
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust:+15.01/-15.05
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: 4.96
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: D-SHIFT 
6.2.15 Check Vacuum Pump Diaphrams			Completed: x
6.2.16 Check Vacuum Tank/Pump lines			Completed: x
6.2.17 Check Load Cup Position alignment		Completed: D-SHIFT 
6.2.18 Check Load Cup Height alignment                  Completed: D-SHIFT 
6.2.19 Check Robot alignments			        Completed:  BJ
6.2.20 Check Muffin Fans for proper operation           Completed:  X
Comments:  Pump diaphrams were checked, need replacement. Could not locate
           part # 
    
--------------------------------------------------------------------------------
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 26
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 22
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A*
                                                        newer model doesn't
                                                        have air driven
                                                        motor                
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 14
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 30
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 52
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 82
6.1.19 Check Drip Pan for moisture/contamination        Completed:  X
6.1.20 Check tubing/fittings for fluid leaks            Completed:  BJ
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  BJ
6.1.22 Check stations/components for contamination	Completed:  D-SHIFT 
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 5
6.1.24 Clean and lubricate the Scrubber rails		Completed:  BJ
6.1.25 Clean and lubricate the Paddle rails		Completed:  BJ
6.1.26 Clean Conditioning Wheel and Housing             Completed:  X
6.1.27 Scrub clean the Polish area tub and walls        Completed:  X
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  D-SHIFT 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  X
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  X
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  X
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  X
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   X
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:  X
6.1.35 Clean the slurry delivery tube                   Completed:  X
6.1.36 Check chiller fluid resevoir for proper level    Completed: BJ
Comments:
                                          
                 
                                                                    
 | 
| 20.58 | WW16 WEEKLY PM | FABSIX::L_SHKOLNIKOV |  | Thu Oct 17 1996 23:49 | 88 | 
|  | 
          SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
    
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 10/17/96          TOOL: CMP.B2            TECH/SHIFT: D - SHIFT
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82psi
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85psi 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 25psi
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40psi 
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22psi
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35psi
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30psi
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40psi 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2psi
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20psi 
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17psi 
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50psi
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60psi
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27psi
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80psi
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 52psi
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80psi
6.1.19 Check Drip Pan for moisture/contamination        Completed: ls
6.1.20 Check tubing/fittings for fluid leaks            Completed: ls
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: ls
6.1.22 Check stations/components for contamination	Completed: ls
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8psi 
6.1.24 Clean and lubricate the Scrubber rails		Completed: ls
6.1.25 Clean and lubricate the Paddle rails		Completed: ls
6.1.26 Clean Conditioning Wheel and Housing             Completed: ls
6.1.27 Scrub clean the Polish area tub and walls        Completed: ls
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: ls
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: ls
6.1.30 Check slurry pump hoses and connectors for leaks Completed: ls
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: ls
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: ls
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed  ls
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed: ls
6.1.35 Clean the slurry delivery tube                   Completed: n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed: DW
Comments:
P.M started on 10/17/96 by Dave Whitford
       ____________________________________________________________
    
 | 
| 20.59 | WW17 WEEKLY PM COMPLETE | FABSIX::L_SHKOLNIKOV |  | Thu Oct 24 1996 22:01 | 92 | 
|  | 
          SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
    
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 10/24/96          TOOL: CMP.B2            TECH/SHIFT: LS./ D - SHIFT
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82psi
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 86psi 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 27psi
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40psi 
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23psi
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35psi
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30psi
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40psi 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2psi
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20psi 
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 16psi 
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50psi
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60psi
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27psi
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80psi
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50psi
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80psi
6.1.19 Check Drip Pan for moisture/contamination        Completed: X 
6.1.20 Check tubing/fittings for fluid leaks            Completed: X 
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: X 
6.1.22 Check stations/components for contamination	Completed: X 
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8psi 
6.1.24 Clean and lubricate the Scrubber rails		Completed: X 
6.1.25 Clean and lubricate the Paddle rails		Completed: X 
6.1.26 Clean Conditioning Wheel and Housing             Completed: X 
6.1.27 Scrub clean the Polish area tub and walls        Completed: X 
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: X 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: X 
6.1.30 Check slurry pump hoses and connectors for leaks Completed: X 
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: X 
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: X 
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed  X 
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed: X  
6.1.35 Clean the slurry delivery tube                   Completed: n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed: X  
Comment:  DURING THE PM FOUND THAT SOME CABLES WHICH GOES FROM FRAME
          TO FLEX TRACK (I/O MANIFOLD) ARE DAMAGED - MISSING AND DAMAGED
          INSULATION  (AI/O #3, DI/O #7). I PUT WHITE TAPE ON THEM.
          WILL TALK TO EE IN THE MORNING TO HAVE THIS CABLES ON ORDER
           
                       
       ____________________________________________________________
    
 | 
| 20.60 | WW XVIII - Weekly Completed | SUBPAC::LANDRY |  | Sun Oct 27 1996 14:28 | 84 | 
|  |           SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 10/27/96          TOOL: CMP.B2            TECH/SHIFT:   Landry
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82 psi
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 86 psi 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 25 psi
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 psi 
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22 psi
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 psi
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2 psi
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 psi 
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 20 psi 
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 psi
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55 psi
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 11 psi
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80 psi
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 50 psi
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 psi
6.1.19 Check Drip Pan for moisture/contamination        Completed: X 
6.1.20 Check tubing/fittings for fluid leaks            Completed: X 
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: X 
6.1.22 Check stations/components for contamination	Completed: X 
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 6 psi 
6.1.24 Clean and lubricate the Scrubber rails		Completed: X 
6.1.25 Clean and lubricate the Paddle rails		Completed: X 
6.1.26 Clean Conditioning Wheel and Housing             Completed: X 
6.1.27 Scrub clean the Polish area tub and walls        Completed: X 
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: X 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: X 
6.1.30 Check slurry pump hoses and connectors for leaks Completed: X 
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: X 
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: X 
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed  X 
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed: X  
6.1.35 Clean the slurry delivery tube                   Completed: n/a
6.1.36 Check chiller fluid resevoir for proper level    Completed: X  
Comments:  6.1.11 N/A due to the paddle for this system is motorized, not
                  pneumatically driven
           6.1.35 N/A due to modification that has eliminated this feature
 | 
| 20.61 | MONTHLY PM COMPLETED FOR WW19 | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Fri Nov 08 1996 06:52 | 153 | 
|  | 
    
    
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
BJ = Brian Jubinville
LS = Leon Shkolnikov
                                           	
6.2.1  Change Peristaltic Pump Lines			Completed: LS
6.2.2  Clean Polish area tub drains			Completed: BJ
6.2.3  Check Polish Table Belt for defects		Completed: BJ
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: LS/BJ
       Down Frc: Head 1 Pre-Adj: 383 Post-adj: 377
                 Head 2 Pre-Adj: 376 Post-adj: 377
                 Head 3 Pre-Adj: 381 Post-adj: 377
                 Head 4 Pre-Adj: 384 Post-adj: 377
                 Head 5 Pre-Adj: 372 Post-adj: 377
6.2.5  Perform Down Force Calibration on Conditioner    Completed: LS/BJ
       Actual Down Force Pre-Adj: 95 lbs
       Actual Down Force Post-Adj: 77 lbs
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: BJ
6.2.7  Check the Load Flipper alignment			Completed: BJ
6.2.8  Check the Unload Flipper alignment		Completed: BJ
6.2.9  Check the Elevator alignment                     Completed: BJ
6.2.10 Check wafer unload, from Index table to cassette Completed: BJ 
6.2.11 Check the +24 Volt power supply    Pre-Adjust: 23.4V Post: 24.01 BJ 
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: 15/-15 BJ 
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: 5V BJ 
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: 30.1
6.2.15 Check Vacuum Pump Diaphrams			Completed: LS/BJ  
6.2.16 Check Vacuum Tank/Pump lines			Completed: LS/BJ  
6.2.17 Check Load Cup Position alignment		Completed: LS/BJ  
6.2.18 Check Load Cup Height alignment                  Completed: LS/BJ  
6.2.19 Check Robot alignments			        Completed: BJ
6.2.20 Check Muffin Fans for proper operation           Completed: LS/BJ  
Comments:
    
          SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80 psi BJ
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85 psi BJ 
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 20 psi BJ
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 psi BJ 
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23 psi BJ
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 psi BJ
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi BJ
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi BJ 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2 psi BJ
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 psi BJ 
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a  BJ
       (paddle not air driven on this tool)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17 psi BJ 
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 psi BJ
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60 psi BJ
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 psi BJ
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80 psi BJ
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55 psi BJ
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 psi BJ
6.1.19 Check Drip Pan for moisture/contamination        Completed:  LS/BJ  
6.1.20 Check tubing/fittings for fluid leaks            Completed:  BJ 
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  BJ
6.1.22 Check stations/components for contamination	Completed:  LS/BJ  
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 10 psi BJ 
6.1.24 Clean and lubricate the Scrubber rails		Completed:  BJ 
6.1.25 Clean and lubricate the Paddle rails		Completed:  BJ
6.1.26 Clean Conditioning Wheel and Housing             Completed:  LS/BJ  
6.1.27 Scrub clean the Polish area tub and walls        Completed:  LS/BJ  
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  LS/BJ  
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  LS/BJ  
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  LS/BJ  
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  LS/BJ  
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  BJ 
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   LS/BJ  
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed:  LS/BJ   
6.1.35 Clean the slurry delivery tube                   Completed: n/a  BJ
       (Tool modified, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed:  BJ  
Comments: 
    
 | 
| 20.62 | WEEKLY PM COMPLETED FOR WW20 | FABSIX::L_SHKOLNIKOV |  | Thu Nov 14 1996 06:03 | 84 | 
|  |           SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 11/14/96          TOOL: CMP.B2            TECH/SHIFT: Jubinville (BJ)
                                                            Shkolnikov (LS)
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85 psi BJ
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 80 psi BJ
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 22 psi BJ
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 psi BJ
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23 psi BJ
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 psi BJ
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi BJ
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi BJ
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2 psi BJ
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 psi BJ
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a BJ
       (L/R paddle now motor driven, no air required)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17 psi BJ
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 psi BJ
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60 psi BJ
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 26 psi BJ
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80 psi BJ
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 48 psi BJ
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 psi BJ
6.1.19 Check Drip Pan for moisture/contamination        Completed: LS
6.1.20 Check tubing/fittings for fluid leaks            Completed: BJ 
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: BJ 
6.1.22 Check stations/components for contamination	Completed: LS/BJ
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 10 psi BJ
6.1.24 Clean and lubricate the Scrubber rails		Completed: BJ 
6.1.25 Clean and lubricate the Paddle rails		Completed: BJ 
6.1.26 Clean Conditioning Wheel and Housing             Completed: LS
6.1.27 Scrub clean the Polish area tub and walls        Completed: BJ
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: BJ 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: LS 
6.1.30 Check slurry pump hoses and connectors for leaks Completed: LS 
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: LS 
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: BJ 
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed  LS/BJ
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed: BJ  
6.1.35 Clean the slurry delivery tube                   Completed: n/a BJ
       (Tool upgraded, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed: BJ
Comments:  
 | 
| 20.63 | WEEKLY PM FOR WW21 COMPLETED | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Wed Nov 20 1996 22:42 | 84 | 
|  |           SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
DATE: 11/20/96          TOOL: CMP.B2            TECH/SHIFT: Jubinville (BJ)
                                                            Whitford   (DW)
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 85 psi DW
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 80 psi DW
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 24 psi DW
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 psi DW 
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 22 psi DW
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 36 psi DW 
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi DW 
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi DW
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2 psi DW
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 psi DW 
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a BJ
       (L/R paddle now motor driven, no air required)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15 psi DW
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 psi DW 
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60 psi DW 
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 psi DW 
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80 psi DW 
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 48 psi DW 
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 psi DW 
6.1.19 Check Drip Pan for moisture/contamination        Completed: BJ 
6.1.20 Check tubing/fittings for fluid leaks            Completed: BJ   
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: BJ   
6.1.22 Check stations/components for contamination	Completed: BJ/DW 
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 10 psi 
6.1.24 Clean and lubricate the Scrubber rails		Completed: DW
6.1.25 Clean and lubricate the Paddle rails		Completed: DW  
6.1.26 Clean Conditioning Wheel and Housing             Completed: BJ 
6.1.27 Scrub clean the Polish area tub and walls        Completed: BJ/DW 
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: BJ   
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: DW  
6.1.30 Check slurry pump hoses and connectors for leaks Completed: DW  
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: BJ  
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: BJ   
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed  BJ  
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed: BJ   
6.1.35 Clean the slurry delivery tube                   Completed: n/a BJ
       (Tool upgraded, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed: BJ
Comments:  
 | 
| 20.64 | weekly pm complete | FABSIX::O_WHITFORD | Quticherwhinin' | Tue Nov 26 1996 22:53 | 87 | 
|  | 
 SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
    
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Weekly P.M.    <WW22>    CMP.B2        11/26/96             Tech   Dave Whitford
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:    80
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:    57
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:    20 
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:    40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust:    22 
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:    36
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:    30
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:    40
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust:    3.2  
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust:    20
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:    na
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust:    17
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:    50 
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust:    62
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust:    27 
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:    80 
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:    48
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust:    80 
6.1.19 Check Drip Pan for moisture/contamination        Completed:     DW
6.1.20 Check tubing/fittings for fluid leaks            Completed:     DW
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:     DW
6.1.22 Check stations/components for contamination	Completed:     DW
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust:    DW
6.1.24 Clean and lubricate the Scrubber rails		Completed:     DW
6.1.25 Clean and lubricate the Paddle rails		Completed:     DW
6.1.26 Clean Conditioning Wheel and Housing             Completed:     DW
6.1.27 Scrub clean the Polish area tub and walls        Completed:     DW
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:     DW
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:     DW
6.1.30 Check slurry pump hoses and connectors for leaks Completed:     DW
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:     DW
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:     DW
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed      DW
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:     DW
6.1.35 Clean the slurry delivery tube                   Completed:     DW
6.1.36 Check chiller fluid resevoir for proper level    Completed:     DW
Comments:
       ____________________________________________________________
    
 | 
| 20.65 | WW23 Monthly PM complete. | FABSIX::L_SHKOLNIKOV |  | Fri Dec 06 1996 00:55 | 153 | 
|  | 
    
    
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
DW = Dave Whitford   
LS = Leon Shkolnikov
                                           	
6.2.1  Change Peristaltic Pump Lines			Completed: WHITFORD    
6.2.2  Clean Polish area tub drains			Completed: WHITFORD
6.2.3  Check Polish Table Belt for defects		Completed: SHKOLNIKOV   
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: SHKOLNIKOV
                                                                   WHITFORD
       Down Frc: Head 1 Pre-Adj: 375 Post-adj: 377 lbs
                 Head 2 Pre-Adj: 375 Post-adj: 377 lbs
                 Head 3 Pre-Adj: 374 Post-adj: 377 lbs
                 Head 4 Pre-Adj: 394 Post-adj: 377 lbs
                 Head 5 Pre-Adj: 379 Post-adj: 377 lbs
6.2.5  Perform Down Force Calibration on Conditioner    Completed: LS/DW 
       Actual Down Force Pre-Adj:  77 lbs
       Actual Down Force Post-Adj: 77 lbs
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: LS
6.2.7  Check the Load Flipper alignment			Completed: LS
6.2.8  Check the Unload Flipper alignment		Completed: DW
                                                                   
6.2.9  Check the Elevator alignment                     Completed: LS
6.2.10 Check wafer unload, from Index table to cassette Completed: DW
6.2.11 Check the +24 Volt power supply    Pre-Adjust: 23.7V   Post: 23.91 V
6.2.12 Check the +/- 15 Volt power supply               Pre-Adjust: +/-15.04 V
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: 4.96 V
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed:  31
6.2.15 Check Vacuum Pump Diaphrams			Completed:  LS
6.2.16 Check Vacuum Tank/Pump lines			Completed:  LS
6.2.17 Check Load Cup Position alignment		Completed:  LS/DW
6.2.18 Check Load Cup Height alignment                  Completed:  LS/DW
6.2.19 Check Robot alignments			        Completed:  LS
6.2.20 Check Muffin Fans for proper operation           Completed:  LS
Comments:
    
          SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80 psi
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 85 psi
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 20 psi
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 psi
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 23 psi
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 psi
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 psi
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 40 psi 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 3.2 psi
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 psi
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a 
       (paddle not air driven on this tool)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 17 psi
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 psi
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 60 psi
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 psi
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 80 psi
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 55 psi
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 psi
6.1.19 Check Drip Pan for moisture/contamination        Completed:  LS
6.1.20 Check tubing/fittings for fluid leaks            Completed:  LS
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  LS
6.1.22 Check stations/components for contamination	Completed:  LS
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8 psi
6.1.24 Clean and lubricate the Scrubber rails		Completed:  LS
6.1.25 Clean and lubricate the Paddle rails		Completed:  LS
6.1.26 Clean Conditioning Wheel and Housing             Completed:  DW
6.1.27 Scrub clean the Polish area tub and walls        Completed:  LS/DW
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  LS/DW
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  LS
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  DW
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  LS
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  LS
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed   LS
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed:  DW
6.1.35 Clean the slurry delivery tube                   Completed: n/a
       (Tool modified, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed:  LS
Comments: 
    
 | 
| 20.66 | Weekly PM Check Sheet (WW24) | ASDG::POIRIER |  | Fri Dec 13 1996 18:11 | 91 | 
|  |                                                                                
 SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
    
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Weekly P.M.    <WW24>    CMP.B2        12/11/96        Techs: Brian Jubinville
                                       12/13/96               John Poirier
6.1.1  Check incoming CDA pressure for 80 PSI	      Pre-adjust: 80/Jubinville
6.1.2  Check incoming N2 pressure for 80 PSI          Pre-adjust: 56/Jubinville
6.1.3  Check incoming DI Water pressure for 20 PSI    Pre-adjust: 22/Jubinville 
6.1.4  Check Load Cup pressure for 45 PSI             Pre-adjust: 40/Jubinville
6.1.5  Check Pad Condition Balance pressure 15-30 PSI Pre-adjust: 22/Jubinville 
6.1.6  Check Pad Conditioner Up pressure for 35 PSI   Pre-adjust: 35/Jubinville
6.1.7  Check Carrier Up pressure for 30 PSI	      Pre-adjust: 30/Jubinville 
                                                                      
6.1.8  Check Miscellaneous pressure for 40 PSI	      Pre-adjust: 40/Jubinville
    
6.1.9  Check Head Balance pressure for 2-6 PSI	      Pre-adjust: 3.2/Jubinville
    
6.1.10 Check Alignment Fixture pressure for 20 PSI    Pre-adjust: 20/Jubinville
6.1.11 Check Transport Paddle L/R pressure for 30 PSI Pre-adjust: N/A-Jubinville
6.1.12 Check Transport Paddle U/D pressure for 20 PSI Pre-adjust: 17/Jubinville
6.1.13 Check Open Load Flipper pressure for 50 PSI    Pre-adjust: 50/Jubinville 
6.1.14 Check Open Unload Flipper pressure for 50 PSI  Pre-adjust: 60/Jubinville
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI  Pre-adjust: 26/Jubinville 
6.1.16 Check Wafer Scrub Down pressure for 80 PSI     Pre-adjust: 80/Jubinville 
6.1.17 Check Scrubber In/Out pressure for 50 PSI      Pre-adjust: 48/Jubinville
6.1.18 Check MHTA pressure for 80 PSI		      Pre-adjust: 80/Jubinville 
6.1.19 Check Drip Pan for moisture/contamination      Completed:  Poirier  
6.1.20 Check tubing/fittings for fluid leaks          Completed:  Jubinville
6.1.21 Check tubing/fittings for pneumatic leaks      Completed:  Jubinville
6.1.22 Check stations/components for contamination    Completed:  Poirier  
6.1.23 Check incoming Chilled Water pressure <10 PSI  Pre-adjust: 8/Jubinville
6.1.24 Clean and lubricate the Scrubber rails	      Completed:  Jubinville
6.1.25 Clean and lubricate the Paddle rails	      Completed:  Jubinville
6.1.26 Clean Conditioning Wheel and Housing           Completed:  Poirier   
6.1.27 Scrub clean the Polish area tub and walls      Completed:  Poirier   
6.1.28 Remove all Load and Unload cups and clean      Completed:  Poirier   
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO   Completed:  Poirier   
6.1.30 Check slurry hoses and connectors for leaks    Completed:  Poirier     
6.1.31 Remove and clean the Vacuum system Check Valve Completed:  N/A-Jubinville
6.1.32 Check Carrier clean brushes for defects        Completed:  Poirier    
6.1.33 Wipe the MHTA and covers with Isopropyl        Completed   Poirier
6.1.34 Wipe the Process Area plexiglas doors w/Iso    Completed:  Poirier
6.1.35 Clean the slurry delivery tube                 Completed:  N/A-Jubinville
6.1.36 Check chiller fluid resevoir for proper level  Completed:  Jubinville
Comments:
N/A 6.1.11 - The air pressure reading for the Transport Paddle applies
             to CMP.B1 only.
    
N/A 6.1.31 - The Vacuum System Check Valve has been removed from the tool. 
N/A 6.1.35 - The Slurry Delivery Tube has been removed from the tool.
 | 
| 20.67 | WEEKLY WW25 | FABSIX::M_RIDLON | Eliminate the oblivious | Tue Dec 17 1996 04:32 | 87 | 
|  |  SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Weekly P.M.    <WW25>    CMP.B2        12/17/96    Techs: Ridlon/R.Poirier
                                       
6.1.1  Check incoming CDA pressure for 80 PSI	      Pre-adjust: 80
6.1.2  Check incoming N2 pressure for 80 PSI          Pre-adjust: 80
6.1.3  Check incoming DI Water pressure for 20 PSI    Pre-adjust: 26
6.1.4  Check Load Cup pressure for 45 PSI             Pre-adjust: 40
6.1.5  Check Pad Condition Balance pressure 15-30 PSI Pre-adjust: 23
6.1.6  Check Pad Conditioner Up pressure for 35 PSI   Pre-adjust: 35
6.1.7  Check Carrier Up pressure for 30 PSI	      Pre-adjust: 30
                                                                      
6.1.8  Check Miscellaneous pressure for 40 PSI	      Pre-adjust: 40
    
6.1.9  Check Head Balance pressure for 2-6 PSI	      Pre-adjust: 3.2
    
6.1.10 Check Alignment Fixture pressure for 20 PSI    Pre-adjust: 21
6.1.11 Check Transport Paddle L/R pressure for 30 PSI Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI Pre-adjust: 19
6.1.13 Check Open Load Flipper pressure for 50 PSI    Pre-adjust: 50
6.1.14 Check Open Unload Flipper pressure for 50 PSI  Pre-adjust: 60
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI  Pre-adjust: 27
6.1.16 Check Wafer Scrub Down pressure for 80 PSI     Pre-adjust: 80
6.1.17 Check Scrubber In/Out pressure for 50 PSI      Pre-adjust: 50
6.1.18 Check MHTA pressure for 80 PSI		      Pre-adjust: 80
6.1.19 Check Drip Pan for moisture/contamination      Completed:  RP
6.1.20 Check tubing/fittings for fluid leaks          Completed:  RP
6.1.21 Check tubing/fittings for pneumatic leaks      Completed:  RP
6.1.22 Check stations/components for contamination    Completed:  RP
6.1.23 Check incoming Chilled Water pressure <10 PSI  Pre-adjust: 8
6.1.24 Clean and lubricate the Scrubber rails	      Completed:  MR
6.1.25 Clean and lubricate the Paddle rails	      Completed:  MR
6.1.26 Clean Conditioning Wheel and Housing           Completed:  MR
6.1.27 Scrub clean the Polish area tub and walls      Completed:  RP
6.1.28 Remove all Load and Unload cups and clean      Completed:  RP/MR
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO   Completed:  RP
6.1.30 Check slurry hoses and connectors for leaks    Completed:  MR
6.1.31 Remove and clean the Vacuum system Check Valve Completed:  N/A
6.1.32 Check Carrier clean brushes for defects        Completed:  MR/RP
6.1.33 Wipe the MHTA and covers with Isopropyl        Completed   MR/RP
6.1.34 Wipe the Process Area plexiglas doors w/Iso    Completed:  MR/RP
6.1.35 Clean the slurry delivery tube                 Completed:  N/A
6.1.36 Check chiller fluid resevoir for proper level  Completed:  MR
Comments:
N/A 6.1.11 - The air pressure reading for the Transport Paddle applies
             to CMP.B1 only.
    
N/A 6.1.31 - The Vacuum System Check Valve has been removed from the tool. 
                    
N/A 6.1.35 - The Slurry Delivery Tube has been removed from the tool.
 | 
| 20.68 | WW26 Weekly PM | FABSIX::R_POIRIER |  | Sun Dec 22 1996 06:04 | 90 | 
|  | --------------------------------------------------------------------------------
 SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Weekly P.M.    <WW26>    CMP.B2        12/22/96    Techs: Ridlon/R.Poirier
                                       
6.1.1  Check incoming CDA pressure for 80 PSI	      Pre-adjust: 80 RP
6.1.2  Check incoming N2 pressure for 80 PSI          Pre-adjust: 80 RP
6.1.3  Check incoming DI Water pressure for 20 PSI    Pre-adjust: 26 RP
6.1.4  Check Load Cup pressure for 45 PSI             Pre-adjust: 40 RP
6.1.5  Check Pad Condition Balance pressure 15-30 PSI Pre-adjust: 23 RP
6.1.6  Check Pad Conditioner Up pressure for 35 PSI   Pre-adjust: 35 RP
6.1.7  Check Carrier Up pressure for 30 PSI	      Pre-adjust: 30 RP
                                                                      
6.1.8  Check Miscellaneous pressure for 40 PSI	      Pre-adjust: 40 RP
    
6.1.9  Check Head Balance pressure for 2-6 PSI	      Pre-adjust: 3.2 RP
    
6.1.10 Check Alignment Fixture pressure for 20 PSI    Pre-adjust: 19 RP
6.1.11 Check Transport Paddle L/R pressure for 30 PSI Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI Pre-adjust: 19 RP
6.1.13 Check Open Load Flipper pressure for 50 PSI    Pre-adjust: 50 RP
6.1.14 Check Open Unload Flipper pressure for 50 PSI  Pre-adjust: 60 RP
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI  Pre-adjust: 27 RP
6.1.16 Check Wafer Scrub Down pressure for 80 PSI     Pre-adjust: 80 RP
6.1.17 Check Scrubber In/Out pressure for 50 PSI      Pre-adjust: 50 RP
6.1.18 Check MHTA pressure for 80 PSI		      Pre-adjust: 80 RP
6.1.19 Check Drip Pan for moisture/contamination      Completed:  RP
6.1.20 Check tubing/fittings for fluid leaks          Completed:  RP
6.1.21 Check tubing/fittings for pneumatic leaks      Completed:  RP
6.1.22 Check stations/components for contamination    Completed:  RP
6.1.23 Check incoming Chilled Water pressure <10 PSI  Pre-adjust: 6 RP
6.1.24 Clean and lubricate the Scrubber rails	      Completed:  RP
6.1.25 Clean and lubricate the Paddle rails	      Completed:  RP
6.1.26 Clean Conditioning Wheel and Housing           Completed:  MR
6.1.27 Scrub clean the Polish area tub and walls      Completed:  MR
6.1.28 Remove all Load and Unload cups and clean      Completed:  RP/MR
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO   Completed:  RP
6.1.30 Check slurry hoses and connectors for leaks    Completed:  MR
6.1.31 Remove and clean the Vacuum system Check Valve Completed:  N/A
6.1.32 Check Carrier clean brushes for defects        Completed:  MR/RP
6.1.33 Wipe the MHTA and covers with Isopropyl        Completed   MR/RP
6.1.34 Wipe the Process Area plexiglas doors w/Iso    Completed:  MR/RP
6.1.35 Clean the slurry delivery tube                 Completed:  N/A
6.1.36 Check chiller fluid resevoir for proper level  Completed:  RP
Comments:
N/A 6.1.11 - The air pressure reading for the Transport Paddle applies
             to CMP.B1 only.
    
N/A 6.1.31 - The Vacuum System Check Valve has been removed from the tool. 
                    
N/A 6.1.35 - The Slurry Delivery Tube has been removed from the tool.
	Engineer informed of all N/A's
 | 
| 20.69 | WW27 Weekly PM completed | FABSIX::R_POIRIER |  | Tue Dec 31 1996 02:17 | 91 | 
|  |                            Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Weekly P.M.    <WW27>    CMP.B2        12/30/96    Techs: Mitch Ridlon
							  Roger Poirier
                                       
6.1.1  Check incoming CDA pressure for 80 PSI	      Pre-adjust: 80 RP
6.1.2  Check incoming N2 pressure for 80 PSI          Pre-adjust: 82 RP
6.1.3  Check incoming DI Water pressure for 20 PSI    Pre-adjust: 20 RP
6.1.4  Check Load Cup pressure for 45 PSI             Pre-adjust: 40 RP
6.1.5  Check Pad Condition Balance pressure 15-30 PSI Pre-adjust: 23 RP
6.1.6  Check Pad Conditioner Up pressure for 35 PSI   Pre-adjust: 35 RP
6.1.7  Check Carrier Up pressure for 30 PSI	      Pre-adjust: 30 RP
                                                                      
6.1.8  Check Miscellaneous pressure for 40 PSI	      Pre-adjust: 40 RP
    
6.1.9  Check Head Balance pressure for 2-6 PSI	      Pre-adjust: 3  RP
    
6.1.10 Check Alignment Fixture pressure for 20 PSI    Pre-adjust: 18 RP
6.1.11 Check Transport Paddle L/R pressure for 30 PSI Pre-adjust: N/A
6.1.12 Check Transport Paddle U/D pressure for 20 PSI Pre-adjust: 18 RP
6.1.13 Check Open Load Flipper pressure for 50 PSI    Pre-adjust: 50 RP
6.1.14 Check Open Unload Flipper pressure for 50 PSI  Pre-adjust: 60 RP
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI  Pre-adjust: 28 RP
6.1.16 Check Wafer Scrub Down pressure for 80 PSI     Pre-adjust: 80 RP
6.1.17 Check Scrubber In/Out pressure for 50 PSI      Pre-adjust: 50 RP
6.1.18 Check MHTA pressure for 80 PSI		      Pre-adjust: 80 RP
6.1.19 Check Drip Pan for moisture/contamination      Completed:  RP/MR
6.1.20 Check tubing/fittings for fluid leaks          Completed:  RP/MR
6.1.21 Check tubing/fittings for pneumatic leaks      Completed:  RP/MR
6.1.22 Check stations/components for contamination    Completed:  RP/MR
6.1.23 Check incoming Chilled Water pressure <10 PSI  Pre-adjust: 6.0 RP
6.1.24 Clean and lubricate the Scrubber rails	      Completed:  MR
6.1.25 Clean and lubricate the Paddle rails	      Completed:  MR
6.1.26 Clean Conditioning Wheel and Housing           Completed:  MR
6.1.27 Scrub clean the Polish area tub and walls      Completed:  MR/RP
6.1.28 Remove all Load and Unload cups and clean      Completed:  RP/MR
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO   Completed:  RP
6.1.30 Check slurry hoses and connectors for leaks    Completed:  MR
6.1.31 Remove and clean the Vacuum system Check Valve Completed:  N/A
6.1.32 Check Carrier clean brushes for defects        Completed:  MR/RP
6.1.33 Wipe the MHTA and covers with Isopropyl        Completed   MR/RP
6.1.34 Wipe the Process Area plexiglas doors w/Iso    Completed:  MR/RP
6.1.35 Clean the slurry delivery tube                 Completed:  N/A
6.1.36 Check chiller fluid resevoir for proper level  Completed:  RP
Comments:
N/A 6.1.11 - The air pressure reading for the Transport Paddle applies
             to CMP.B1 only.
    
N/A 6.1.31 - The Vacuum System Check Valve has been removed from the tool. 
                    
N/A 6.1.35 - The Slurry Delivery Tube has been removed from the tool.
DG-I/O cables 5,6,7,8 need to be replaced due to stress.
	Engineer informed of all N/A's
 | 
| 20.70 | CMP.B2 shutdown checksheet completed | FABSIX::R_GEE |  | Tue Dec 31 1996 15:40 | 28 | 
|  | 
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                        CMP.B SHUT DOWN CHECK SHEET         Tech: _Tim Landry
								  _Bob Gee
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
								 INIT / DATE
1) SCRUB SIDES OF CARRIERS				       TL_BG_/_12/31/96
2) RUN CARRIER BLOW OFF FOR 30 SECONDS			       TL_BG_/_12/31/96
3) REMOVE ALL CARRIERS					       TL_BG_/_12/31/96
4) PLACE WIPES UNDER CARRIER FILMS AND LAY CARRIERS DI TANK    TL_BG_/_12/31/96
5) IF POWER TO SLURRY SYSTEM IS GOING TO BE LOST, CONTACT 
   ASHLAND CHEMICAL AND HAVE SLURRY SYSTEM PURGED AND CHARGED 
   WITH DI WATER.					       TL_BG_/_12/31/96
6) CLEAN ENTIRE SYSTEM OF DRIED SLURRY 			       TL_BG_/_12/31/96
7) REMOVE CONDITIONER AND CLEAN				       TL_BG_/_12/31/96
8) CYCLE/RINSE ALL DI FUNCTIONS: SPRAY NOZZLES, SLURRY PUMPS,
   CONDITIONER RINSE, ELEVATOR TANKS.			       TL_BG_/_12/31/96
9) SHUT OFF DI BEHIND SYSTEM (ROTATE 3W VLV TO FULL RETURN)    TL_BG_/_12/31/96
10) DRAIN ELEVATOR AND CONDITIONER TUBE			       TL_BG_/_12/31/96
11) REMOVE PADS, AND CLEAN AND DRY TABLES		       TL_BG_/_12/31/96
12) REMOVE SCRUBBER BRUSHES AND SOAK IN DI		       TL_BG_/_12/31/96
13) DRY ENTIRE SYSTEM OF ANY STANDING WATER		       TL_BG_/_12/31/96
14) POWER DOWN SYSTEM.
 | 
| 20.71 | MONTHLY PM FOR WW28 COMPLETED | FABSIX::L_SHKOLNIKOV |  | Wed Jan 08 1997 01:15 | 153 | 
|  | 
    
    
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev D
Date: 01.07.97      Tool: CMP.B2             Tech/shift:  DW - Olin  Whitford   
                                                          LS - Leon  Shkolnikov
                                           	          BJ - Brian Jubinville
6.2.1  Change Peristaltic Pump Lines			Completed: DW
6.2.2  Clean Polish area tub drains			Completed: BJ/LS
6.2.3  Check Polish Table Belt for defects		Completed: LS
6.2.4  Perform Down Force Calibration on all 5 heads    Completed: DW,LS
                                                                  
       Down Frc: Head 1 Pre-Adj: 410 Post-adj: 377 lbs
                 Head 2 Pre-Adj: 415 Post-adj: 377 lbs
                 Head 3 Pre-Adj: 410 Post-adj: 377 lbs
                 Head 4 Pre-Adj: 414 Post-adj: 377 lbs
                 Head 5 Pre-Adj: 411 Post-adj: 377 lbs
6.2.5  Perform Down Force Calibration on Conditioner    Completed: DW/LS
       Actual Down Force Pre-Adj:  79 lbs
       Actual Down Force Post-Adj: 77 lbs
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed:  LS
6.2.7  Check the Load Flipper alignment			Completed:  BJ
6.2.8  Check the Unload Flipper alignment		Completed:  BJ
                                                                   
6.2.9  Check the Elevator alignment                     Completed:  BJ
6.2.10 Check wafer unload, from Index table to cassette Completed:  BJ
6.2.11 Check the +24 Volt power supply    Pre-Adjust: 23.8V   Post: 24.0V LS
6.2.12 Check the +/- 15 Volt power supply           Pre-Adjust: +/-15.04V LS
6.2.13 Check the +5 Volt power supply                   Pre-Adjust: 4.96 V LS
6.2.14 Check Table Rotation Speed @ 30 RPM              Completed: BJ
6.2.15 Check Vacuum Pump Diaphrams			Completed: BJ
6.2.16 Check Vacuum Tank/Pump lines			Completed: LS
6.2.17 Check Load Cup Position alignment		Completed: BJ
6.2.18 Check Load Cup Height alignment                  Completed: BJ
6.2.19 Check Robot alignments			        Completed: LS
6.2.20 Check Muffin Fans for proper operation           Completed: LS
Comments:
    
          SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80 DW
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 55 DW
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 23 DW
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 DW
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 20 DW
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 30 DW
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 DW
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 50 DW 
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 6 BJ
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 DW
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a BJ
       (paddle not air driven on this tool)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 16 DW
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 DW
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55 DW
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 DW
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 25 DW
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 48 DW
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 DW
6.1.19 Check Drip Pan for moisture/contamination        Completed: LS
6.1.20 Check tubing/fittings for fluid leaks            Completed: LS
6.1.21 Check tubing/fittings for pneumatic leaks        Completed: LS
6.1.22 Check stations/components for contamination	Completed: LS
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust:10 psi LS
6.1.24 Clean and lubricate the Scrubber rails		Completed: LS
6.1.25 Clean and lubricate the Paddle rails		Completed: LS
6.1.26 Clean Conditioning Wheel and Housing             Completed: DW
6.1.27 Scrub clean the Polish area tub and walls        Completed: LS/BJ/DW 
6.1.28 Remove all Load and Unload cups and scrub clean  Completed: LS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed: LS
6.1.30 Check slurry pump hoses and connectors for leaks Completed: DW
6.1.31 Remove and clean the Vacuum system Check Valve   Completed: LS
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed: LS
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed: LS  
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed: LS
6.1.35 Clean the slurry delivery tube                   Completed: n/a
       (Tool modified, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed: LS
Comments: 
    
 | 
| 20.72 | WW29 WEEKLY PM COMPLETED. | FABSIX::L_SHKOLNIKOV |  | Thu Jan 16 1997 06:59 | 91 | 
|  | 
    
    
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Date: 01.16.97      Tool: CMP.B2             Tech/shift:  DW - Olin  Whitford   
                                                          LS - Leon  Shkolnikov
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 80 DW     
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 60 DW
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 26 DW
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 DW
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 20 DW
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 DW
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 DW
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 50 DW
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 6  DW
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 DW
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: N/A
       (paddle not air driven on this tool)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15 DW
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 DW
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55 DW
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 DW
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 25 DW
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 45 DW
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 DW
6.1.19 Check Drip Pan for moisture/contamination        Completed:  LS
6.1.20 Check tubing/fittings for fluid leaks            Completed:  LS
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  LS
6.1.22 Check stations/components for contamination	Completed:  LS/DW
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8  DW
6.1.24 Clean and lubricate the Scrubber rails		Completed:  LS
6.1.25 Clean and lubricate the Paddle rails		Completed:  LS
6.1.26 Clean Conditioning Wheel and Housing             Completed:  DW **
6.1.27 Scrub clean the Polish area tub and walls        Completed:  DW/LS
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  LS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  LS
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  LS
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  LS
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  LS
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed:  DW/LS
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed:  DW/LS
6.1.35 Clean the slurry delivery tube                   Completed: n/a
       (Tool modified, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed:  LS
**Comments:  Replaced pad conditioner ring per EE request. Total wafer count on
tool was 60,477
    
 | 
| 20.73 | WW30 WEEKLY PM COMPLETED. | FABSIX::L_SHKOLNIKOV |  | Wed Jan 22 1997 06:51 | 88 | 
|  | 
    
    
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
Date: 01.22.97      Tool: CMP.B2             Tech/shift: Leon  Shkolnikov - LS
    
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust: 82 LS     
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust: 84 LS
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust: 30 LS
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust: 40 LS
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust: 20 LS
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust: 35 LS
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust: 30 LS
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust: 50 LS
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust: 6  LS
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust: 20 LS
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust: n/a *
       (paddle not air driven on this tool)
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust: 15 LS
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust: 50 LS
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust: 55 LS*
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust: 27 LS*
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust: 25 LS*
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust: 45 LS*
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust: 80 LS
6.1.19 Check Drip Pan for moisture/contamination        Completed:  LS
6.1.20 Check tubing/fittings for fluid leaks            Completed:  LS
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:  LS
6.1.22 Check stations/components for contamination	Completed:  LS
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust: 8  LS
6.1.24 Clean and lubricate the Scrubber rails		Completed:  LS
6.1.25 Clean and lubricate the Paddle rails		Completed:  LS
6.1.26 Clean Conditioning Wheel and Housing             Completed:  LS 
6.1.27 Scrub clean the Polish area tub and walls        Completed:  LS
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:  LS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:  LS
6.1.30 Check slurry pump hoses and connectors for leaks Completed:  LS
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:  LS
          (water separator)
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:  LS
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed:  LS
6.1.34 Wipe the Process Area Plexiglas doors w/ISO      Completed:  LS
6.1.35 Clean the slurry delivery tube                   Completed: n/a *
       (Tool modified, no longer uses tube)
6.1.36 Check chiller fluid resevoir for proper level    Completed:  LS
Comments: * SPEC BEING REVISED 
 | 
| 20.74 | CMP.B2 WEEKLY CHECK SHEET (WW31) | ASDG::POIRIER |  | Fri Jan 31 1997 13:55 | 90 | 
|  | 
 SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
  Date: 1/30/97   WW31       RTC Entity: CMP.B2    Tech(s): John Poirier  = JP
                                                            Brad Westphal = BW
   
                           Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev D
6.1.1  Check incoming CDA pressure for 80 PSI		Pre-adjust:  80 JP
6.1.2  Check incoming N2 pressure for 80 PSI            Pre-adjust:  80 JP
6.1.3  Check incoming DI Water pressure for 20 PSI      Pre-adjust:  34 JP
6.1.4  Check Load Cup pressure for 45 PSI		Pre-adjust:  40 JP
6.1.5  Check Pad Condition Balance pressure 15-30 PSI	Pre-adjust:  20 JP
6.1.6  Check Pad Conditioner Up pressure for 35 PSI	Pre-adjust:  35 JP
6.1.7  Check Carrier Up pressure for 30 PSI		Pre-adjust:  30 JP
6.1.8  Check Miscellaneous pressure for 40 PSI		Pre-adjust:  50 JP
6.1.9  Check Head Balance pressure for 2-6 PSI		Pre-adjust:   6 JP
6.1.10 Check Alignment Fixture pressure for 20 PSI      Pre-adjust:  20 JP
6.1.11 Check Transport Paddle L/R pressure for 30 PSI	Pre-adjust:  N/A JP
6.1.12 Check Transport Paddle U/D pressure for 20 PSI	Pre-adjust:  10  JP
6.1.13 Check Open Load Flipper pressure for 50 PSI	Pre-adjust:  50  JP
6.1.14 Check Open Unload Flipper pressure for 50 PSI	Pre-adjust:  50  JP
6.1.15 Check Vacuum Tank Blowout pressure for 15 PSI    Pre-adjust:  26  JP
6.1.16 Check Wafer Scrub Down pressure for 80 PSI	Pre-adjust:  25  JP
6.1.17 Check Scrubber In/Out pressure for 50 PSI	Pre-adjust:  45  JP
6.1.18 Check MHTA pressure for 80 PSI			Pre-adjust:  80  JP
6.1.19 Check Drip Pan for moisture/contamination        Completed:   JP  
6.1.20 Check tubing/fittings for fluid leaks            Completed:   JP
6.1.21 Check tubing/fittings for pneumatic leaks        Completed:   JP
6.1.22 Check stations/components for contamination	Completed:   JP
6.1.23 Check incoming Chilled Water pressure <10 PSI	Pre-adjust:   9
6.1.24 Clean and lubricate the Scrubber rails		Completed:   JP
6.1.25 Clean and lubricate the Paddle rails		Completed:   JP
6.1.26 Clean Conditioning Wheel and Housing             Completed:   BW
6.1.27 Scrub clean the Polish area tub and walls        Completed:   BW
6.1.28 Remove all Load and Unload cups and scrub clean  Completed:   BW
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO     Completed:   JP
6.1.30 Check slurry pump hoses and connectors for leaks Completed:   JP
6.1.31 Remove and clean the Vacuum system Check Valve   Completed:   N/A
6.1.32 Check Carrier clean brushes for defects, rotate  Completed:   JP
6.1.33 Wipe the MHTA and covers with Isopropyl          Completed    JP
6.1.34 Wipe the Process Area plexiglas doors w/Iso      Completed:   JP
6.1.35 Clean the slurry delivery tube                   Completed:   N/A
6.1.36 Check chiller fluid resevoir for proper level    Completed:   JP
Comments: N/A 6.1.11 - This line item refers to CMP.B1 only.
          N/A 6.1.31 - The check valve is no longer used.
    
          N/A 6.1.35 - The slurry delivery tube is no longer used.
 | 
| 20.75 | MONTHLY PM COMPLETED FOR WW32 | SUBPAC::BJUBINVILLE | CMP-6 Equipment Engineering | Wed Feb 05 1997 05:45 | 198 | 
|  | 
                     SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           SPEC# HF60-0172  REV-E 
                        Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev. E 
DATE: 02/04/97      TOOL: CMP.B2       TECHNICIAN(S):  Mitch Ridlon (MR)
                                                       Roger Poirier (RP)
                                                       Brian Jubinville (BJ)
                                                       Dave Whitford (DW)
                                                       Leon Shkolnikov (LS)
START TIME: 22:00          COMPLETED TIME: 00:30
6.2.1  Change Peristaltic Pump Lines and check flow     Completed: RP
                                                             
6.2.2  Clean Polish area tub drains for clogs		Completed: LS,DW
6.2.3  Check all table belts for defects		Completed: RP
6.2.4  Perform Down Force Calibration on all 5 heads   
       to read at +/- 1lbs of 354 lbs.
       NOTE:  The target is 23 lbs. below the actual
       377 lbs. due to the carrier weight minus the
       alignment fixture using the point-to-point
       method as described in the downforce procedure
       in 6.2.4.1 through 6.2.4.13.                     Completed: LS,DW
       Down Frc: Head 1 Pre-Adj: 361  Post-adj: 354
                 Head 2 Pre-Adj: 367  Post-adj: 354
                 Head 3 Pre-Adj: 358  Post-adj: 354
                 Head 4 Pre-Adj: 355  Post-adj: 354
                 Head 5 Pre-Adj: 350  Post-adj: 354
6.2.5  Perform Down Force Calibration on Conditioner    Completed: LS,DW
       to read +/- .5 lbs of 77lbs.
 
       Actual Down Force Pre-Adj: 78lbs
       Actual Down Force Post-Adj: 77lbs
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: RP
6.2.7  Check the Load Flipper alignment			Completed: RP
6.2.8  Check the Unload Flipper alignment		Completed: RP
6.2.9  Check Elevator alignments			Completed: RP
6.2.10 Check wafer unload, from Index table to cassette Completed: RP
6.2.11 Check the +24 Volt power supply for +/- 1V
       of 24V.                        Pre: 24.0  Post: 24.0  Tech: RP
6.2.12 Check the +/- 15 Volt power supply for +/- 1V
       of 15V                       Pre: 15.06 Post: 15.06   Tech: RP
6.2.13 Check the +5 Volt power supply for +/- .5V 
       of 5V.                      Pre: 4.99   Post: 4.99    Tech: RP
6.2.14 Check Table Rotation Speed for +/- 1.5 of 30RPM  Completed: LS/DW 
6.2.15 Check Vacuum Pump Diaphrams			Completed: BJ
6.2.16 Replace liquid separator element                 Completed: BJ
6.2.17 Check Vacuum Tank/Pump lines			Completed: BJ
6.2.18 Check carrier to Load Cup Position alignments    Completed: RP
6.2.19 Check Load Cup Height to carrier alignments      Completed: RP
6.2.20  Check the Robot alignments                      Completed: BJ/LS
                                         
6.2.21 Check Muffin Fans for proper operation           Completed: RP
Comments:
========================================================================
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 02/02/97      TOOL: CMP.B2       TECHNICIAN(S):  Mitch Ridlon (MR)
                                                       Roger Poirier (RP)
                                                       Brian Jubinville (BJ)
                                                       Dave Whitford (DW)
                                                       Leon Shkolnikov (LS)
START TIME:            COMPLETED TIME:
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: RP
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: BJ
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: RP
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: RP
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: RP
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: RP
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: RP
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: RP
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: RP 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: * BJ
       * (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: RP
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: RP
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: RP
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: RP
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: RP
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: RP
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: RP
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: RP
6.1.19 Check Drip Pans for moisture/contamination        Completed: RP
6.1.20 Check tubing/fittings for fluid leaks             Completed: RP 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: RP 
6.1.22 Check stations/components for contamination	 Completed: RP 
                                                                    
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: RP
6.1.24 Clean and lubricate the Scrubber rails		 Completed: RP
6.1.25 Clean and lubricate the Paddle rails		 Completed: RP
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: RP
6.1.27 Scrub clean the Polish area tub and walls         Completed: RP
6.1.28 Remove all Load and Unload cups and scrub clean    
       with 5% hydrogen peroxide.                        Completed: RP,DW,LS,BJ
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: RP
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: RP
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: BJ
6.1.32 Check Carrier clean brushes for defects           Completed: RP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: RP
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: RP
6.1.35 Check chiller fluid resevoir for proper level     Completed: BJ
6.1.36 Check the chiller readout for 24 degrees C.       Completed: BJ
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: LS  
6.1.38 Check the slurry flow alarm.                      Completed: LS/DW/BJ 
Comments:
                                                  
 | 
| 20.76 | ww33 weekly pm completed. | FABSIX::L_SHKOLNIKOV |  | Sat Feb 15 1997 00:13 | 110 | 
|  | 
                                                                         
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE:2/14/97       TOOL ENTITY:CMP.B2        TECH(S): Leon Shkolnikov - LS
                                                                              
                                                     
                                              
    
START TIME: 10:00 pm.       COMPLETED TIME: 12:01 am.
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 LS
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 LS
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 20 LS
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 LS
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 LS
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 LS  
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 LS
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 LS
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:  6 LS
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A  
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 LS  
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 LS
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 55 LS
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 LS
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 LS
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 LS
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 LS
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 LS
6.1.19 Check Drip Pans for moisture/contamination        Completed: LS  
6.1.20 Check tubing/fittings for fluid leaks             Completed: LS  
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: LS  
6.1.22 Check stations/components for contamination	 Completed: LS  
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: LS 
6.1.24 Clean and lubricate the Scrubber rails		 Completed: LS 
6.1.25 Clean and lubricate the Paddle rails		 Completed: LS 
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: LS 
6.1.27 Scrub clean the Polish area tub and walls         Completed: LS 
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: LS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: LS 
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: LS     
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: LS 
6.1.32 Check Carrier clean brushes for defects           Completed: LS 
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: LS 
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: LS 
6.1.35 Check chiller fluid resevoir for proper level     Completed: LS 
6.1.36 Check the chiller readout for 24 degrees C.       Completed: LS
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: LS      
6.1.38 Check the slurry flow alarm.                      Completed: LS  
Comment: (I/O MANIFOLD) AI/O#3 cable slightly damaged. Will notify
         to EE in the morning.
           
                       
    
 | 
| 20.77 | WEEKLY PM FOR WW34 COMPLETED | SUBPAC::BJUBINVILLE | CMP Equipment Engineering | Thu Feb 20 1997 05:07 | 105 | 
|  |                                                                          
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:2/20/97       TOOL ENTITY:CMP.B2        TECH(S): Brian Jubinville - BJ
                                                      Leon Shkolnikov - LS
                                                      Olin Whitford - OW
                            
START TIME: 02:30      COMPLETED TIME: 05:00
    
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 BJ
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 BJ 
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 23 BJ
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 BJ 
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 BJ 
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 BJ  
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 BJ 
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 BJ 
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:  6 BJ 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A  BJ
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 BJ   
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 BJ
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 55 BJ
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 BJ
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 BJ
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 BJ
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 BJ
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 BJ
6.1.19 Check Drip Pans for moisture/contamination        Completed:  LS/BJ
6.1.20 Check tubing/fittings for fluid leaks             Completed:  BJ
6.1.21 Check tubing/fittings for pneumatic leaks         Completed:  BJ
6.1.22 Check stations/components for contamination	 Completed:  LS/BJ
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:  BJ
6.1.24 Clean and lubricate the Scrubber rails		 Completed:  LS
6.1.25 Clean and lubricate the Paddle rails		 Completed:  LS
6.1.26 Remove and clean conditioning Wheel and Housing   Completed:  BJ
6.1.27 Scrub clean the Polish area tub and walls         Completed:  BJ
6.1.28 Remove all Load and Unload cups and scrub clean               BJ
       with hydrogen peroxide.                           Completed: 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed:  BJ
6.1.30 Check slurry pump hoses and connectors for leaks  Completed:  BJ   
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed:  LS
6.1.32 Check Carrier clean brushes for defects           Completed:  BJ
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed:  BJ
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed:  BJ
6.1.35 Check chiller fluid resevoir for proper level     Completed:  BJ
6.1.36 Check the chiller readout for 24 degrees C.       Completed:  BJ
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:  BJ     
6.1.38 Check the slurry flow alarm.                      Completed:  BJ/LS 
Comment:   
                       
         
                                                                          
 | 
| 20.78 | SEMI-A MOVED OUT 1 WEEK | YIELD::TDYER |  | Thu Feb 27 1997 15:18 | 8 | 
|  |     
    SEMI-ANNUAL PM WILL BE PUSHED OUT TO NEXT WEEK 3/3/97. THIS MAJOR PM
    WILL BE PERFORMED DURRING THE INDEX TABLE UPGRADES NEXT WEEK. EEG TO
    PERFORMA WEEKLY PM IN PLACE THIS WEEK.
    
    TIM D.
    EQUIPMENT ENGINEER.
    
 | 
| 20.79 | WW35 WEEKLY PM COMPLETED. | FABSIX::L_SHKOLNIKOV |  | Fri Feb 28 1997 00:22 | 105 | 
|  |                                                                          
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:2/27/97       TOOL ENTITY:CMP.B2        TECH(S): Leon Shkolnikov - LS
                                                      Olin Whitford - OW
                            
START TIME: 09:30      COMPLETED TIME: 12:00
    
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 ls
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 ls 
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 ls
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 ls 
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 ls 
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 ls  
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 ls 
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 ls 
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:  6 ls 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A    
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 ls   
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 ls
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 55 ls
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 ls
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 ls
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 ls
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 ls
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 ls
6.1.19 Check Drip Pans for moisture/contamination        Completed:  LS/DW
6.1.20 Check tubing/fittings for fluid leaks             Completed:  LS
6.1.21 Check tubing/fittings for pneumatic leaks         Completed:  LS
6.1.22 Check stations/components for contamination	 Completed:  LS/DW
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:  LS
6.1.24 Clean and lubricate the Scrubber rails		 Completed:  LS
6.1.25 Clean and lubricate the Paddle rails		 Completed:  LS
6.1.26 Remove and clean conditioning Wheel and Housing   Completed:  DW
6.1.27 Scrub clean the Polish area tub and walls         Completed:  DW
6.1.28 Remove all Load and Unload cups and scrub clean                 
       with hydrogen peroxide.                           Completed:  DW/LS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed:  LS
6.1.30 Check slurry pump hoses and connectors for leaks  Completed:  DW** 
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed:  LS
6.1.32 Check Carrier clean brushes for defects           Completed:  DW/LS
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed:  LS/DW
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed:  DW/LS
6.1.35 Check chiller fluid resevoir for proper level     Completed:  LS
6.1.36 Check the chiller readout for 24 degrees C.       Completed:  LS
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:  LS     
6.1.38 Check the slurry flow alarm.                      Completed:  DW
Comment:  The slurry lines have been replaced and slurry flow calibrated.
                       
         
                                                                          
   
 | 
| 20.80 | ww36 S/A pm completed. | FABSIX::L_SHKOLNIKOV | No more experiments with freedom | Tue Mar 04 1997 21:21 | 234 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                               SPEC# HF60-0172  REV-E    
                         Speedfam Corp. CMP-V Planarizer
     	Semi-Annual Preventative Maintenance Check Sheet, Rev. E
DATE: 3/4/97 TOOL ENTITY: CMP.B2  TECHNICIAN(S):Brendan Finn    =BF 
                                                Bob Gee         =BG
                                                Tim Landry      =TL
						Jim Sadin       =JS 
                                                Leon Shkolnikov =LS
START TIME: 0900 hours         COMPLETED TIME: 09:30 pm. 
6.4.1  Check all interlocks for functionality		Completed: JS
6.4.2  Check all EMO's for functionality		Completed: JS
6.4.3  Lubricate the Rotary Union			Completed: LS
6.4.4  Lubricate the Lead Screw				Completed: LS
6.4.5  Lubricate the Linear Guide Rails			Completed: LS
6.4.6  Lubricate the Idler Pulley			Completed: LS
6.4.7  Rebuild the vacuum pump using the appropriate    
       rebuild kit.                                     Completed: BG
Comments:
=======================================================================
                     SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           SPEC# HF60-0172  REV-E 
                        Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev. E 
DATE: 3/4/97 TOOL ENTITY: CMP.B2  TECHNICIAN(S):Brendan Finn=BF 
                                                Bob Gee     =BG
                                                Tim Landry  =TL
						Jim Sadin   =JS 
START TIME: 0900 hours         COMPLETED TIME: 
6.2.1  Change Peristaltic Pump Lines and check flow     Completed: BG
6.2.2  Clean Polish area tub drains for clogs		Completed: JS
6.2.3  Check all table belts for defects		Completed: BG
6.2.4  Perform Down Force Calibration on all 5 heads   
       to read at +/- 1lbs of 354 lbs.
       NOTE:  The target is 23 lbs. below the actual
       377 lbs. due to the carrier weight minus the
       alignment fixture using the point-to-point
       method as described in the downforce procedure
       in 6.2.4.1 through 6.2.4.13.                     Completed: BF,BG
                                                                   JS,TL
       Down Frc: Head 1 Pre-Adj: 357   Post-adj: 354
                 Head 2 Pre-Adj: 336   Post-adj: 354
                 Head 3 Pre-Adj: 334   Post-adj: 354
                 Head 4 Pre-Adj: 354   Post-adj: 354
                 Head 5 Pre-Adj: 338   Post-adj: 354
6.2.5  Perform Down Force Calibration on Conditioner    Completed: BF,BG
       to read +/- .5 lbs of 77lbs.
 
       Actual Down Force Pre-Adj.  77.4
       Actual Down Force Post-Adj: 77.4
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: JS, TL
6.2.7  Check the Load Flipper alignment			Completed: TL,BF,JS
								   BG,DR
6.2.8  Check the Unload Flipper alignment		Completed: TL,BF,JS
								   BG,DR
6.2.9  Check Elevator alignments			Completed: TL,BF,JS
								   BG
6.2.10 Check wafer unload, from Index table to cassette Completed: TL,BF,JS
								   BG
6.2.11 Check the +24 Volt power supply for +/-1V
       of  24V.                Pre: 24.12  Post: 24.12    Tech: JS,TL
6.2.12 Check the +/- 15 Volt power supply for +/- 1V
       of 15V.                 Pre: +15.03  Post: +15.03  Tech: JS, TL
                               Pre: -15.06  Post: -15.06  
6.2.13 Check the +5 Volt power supply for 4.5 to
       5.5 v.                  Pre: 4.96   Post: 4.96     Tech: JS, TL
6.2.14 Check Table Rotation Speed for +/- 1.5 of 30RPM  Completed:  JS, TL
 
6.2.15 Check Vacuum Pump Diaphrams			Completed: BG
6.2.16 Replace liquid separator filter element          Completed: BG
6.2.17 Check Vacuum Tank/Pump lines			Completed: BG
6.2.18 Check carrier to Load Cup Position alignments    Completed: BF,JS,BG 
                                                                   TL
6.2.19 Check Load Cup Height to carrier alignments      Completed: LS
6.2.20  Check the Robot alignments                      Completed: JS, TL
                                         
6.2.21 Check Muffin Fans for proper operation           Completed: LS
Comments:
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 3/4/97  TOOL ENTITY:  CMP.B2  TECHNICIAN(S):  Brendan Finn (BF)
                                                    Jim Sadin   (JS)
						    Tim Landry  (TL)
						    Bob Gee     (BG)
START TIME:       COMPLETED TIME:
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 82 
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 30
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.2
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/a
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 52
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 26
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45
6.1.19 Check Drip Pans for moisture/contamination        Completed: BG 
6.1.20 Check tubing/fittings for fluid leaks             Completed: BG
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: BG
6.1.22 Check stations/components for contamination	 Completed: TL,BF,JS 
								    BG
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: BF
6.1.24 Clean and lubricate the Scrubber rails		 Completed: BF
6.1.25 Clean and lubricate the Paddle rails		 Completed: BF
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: BG
6.1.27 Scrub clean the Polish area tub and walls         Completed: JS
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: JS/BF/TL/BG
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: BF
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: BF
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: BG
6.1.32 Check Carrier clean brushes for defects           Completed: TL
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: JS
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: BF
6.1.35 Check chiller fluid resevoir for proper level     Completed: BF
6.1.36 Check the chiller readout for 24 degrees C.       Completed: JS
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:  LS
 
6.1.38 Check the slurry flow alarm.                      Completed:  BF
Comments:
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/a
       (Applicable for CMP.B1 only) Does not apply to CMP.B2
6.1.35 Added water to chiller
 | 
| 20.81 | WEEKLY PM FOR WW37 COMPLETED | SUBPAC::BJUBINVILLE | CMP Equipment Engineering | Fri Mar 14 1997 00:59 | 105 | 
|  |                                                                          
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:3/14/97       TOOL ENTITY:CMP.B2        TECH(S): Leon Shkolnikov - LS
                                                      Brian Jubinville - BJ
                            
START TIME: 23:00       COMPLETED TIME: 01:00
    
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 BJ
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 BJ 
                                                                        
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 BJ
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 BJ
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 BJ
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 BJ 
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 BJ 
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 BJ 
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:  6 BJ
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A BJ  
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 BJ   
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 BJ
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 BJ
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 BJ
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 BJ
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 BJ 
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 BJ
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 BJ
6.1.19 Check Drip Pans for moisture/contamination        Completed: LS/BJ 
6.1.20 Check tubing/fittings for fluid leaks             Completed: BJ 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: BJ
                                                                       
6.1.22 Check stations/components for contamination	 Completed: LS/BJ 
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 7 BJ  
                                                                     
6.1.24 Clean and lubricate the Scrubber rails		 Completed: BJ 
6.1.25 Clean and lubricate the Paddle rails		 Completed: BJ 
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: BJ 
6.1.27 Scrub clean the Polish area tub and walls         Completed: BJ
6.1.28 Remove all Load and Unload cups and scrub clean             
       with hydrogen peroxide.                           Completed: LS/BJ 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: BJ 
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: BJ  
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed: BJ 
6.1.32 Check Carrier clean brushes for defects           Completed: BJ 
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: BJ 
                                                                    
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: BJ 
6.1.35 Check chiller fluid resevoir for proper level     Completed: BJ 
6.1.36 Check the chiller readout for 24 degrees C.       Completed: BJ 
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: LS/BJ      
6.1.38 Check the slurry flow alarm.                      Completed: LS/BJ
Comment:  A small puddle of DI was under the tool below the index table
          area.              
         
                                                                          
   
 | 
| 20.82 | WW38 weekly pm completed. | FABSIX::J_SADIN | Freedom isn't free. | Sun Mar 16 1997 13:02 | 104 | 
|  |                                                                          
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:3/16/97       TOOL ENTITY:CMP.B2        TECH(S):  Timothy Landry (TL)
                                                       Brendan Finn   (BF)
                                                       Bob Gee        (BG)
                                                       James Sadin    (JS)
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 JS
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 JS 
                                                                        
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 JS
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 JS
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 JS
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 JS 
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 JS 
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 JS 
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:  6 JS
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A JS  
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 JS   
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 JS
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 JS
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 JS
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 JS
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 21 JS
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 JS
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 JS
6.1.19 Check Drip Pans for moisture/contamination        Completed: TL/BF 
6.1.20 Check tubing/fittings for fluid leaks             Completed: BG 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: BG
                                                                       
6.1.22 Check stations/components for contamination	 Completed: TL/BG 
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: BF  
                                                                     
6.1.24 Clean and lubricate the Scrubber rails		 Completed: BF 
6.1.25 Clean and lubricate the Paddle rails		 Completed: BF 
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: TL 
6.1.27 Scrub clean the Polish area tub and walls         Completed: TL/JS
6.1.28 Remove all Load and Unload cups and scrub clean             
       with hydrogen peroxide.                           Completed: TL/JS/BF/BG 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: TL 
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: BG  
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed: TL 
6.1.32 Check Carrier clean brushes for defects           Completed: JS 
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: TL/JS 
                                                                    
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: TL/JS 
6.1.35 Check chiller fluid resevoir for proper level     Completed: BF 
6.1.36 Check the chiller readout for 24 degrees C.       Completed: BF 
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: TL/JS      
6.1.38 Check the slurry flow alarm.                      Completed: BG/BF
COMMENTS: 
6.1.19 - found small puddle of DI under load cup 4 area of drip pan.
 | 
| 20.83 | WW39 Weekly PM completed | FABSIX::R_POIRIER |  | Wed Mar 26 1997 06:27 | 106 | 
|  | 
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:3/26/97       TOOL ENTITY:CMP.B2        TECH(S):  Roger Poirier  (RP)
                                                       Al Quillen     (AQ)
                                                       
                                                       
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 RP
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 RP
                                                                        
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 RP
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 RP
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 RP
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 RP 
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 RP 
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 RP 
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.2 RP
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A RP  
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 RP   
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 RP
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 RP
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 RP
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 RP
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 22 RP
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 RP
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 RP
6.1.19 Check Drip Pans for moisture/contamination        Completed:  RP/AQ
6.1.20 Check tubing/fittings for fluid leaks             Completed: AQ
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: RP
                                                                       
6.1.22 Check stations/components for contamination	 Completed: RP/AQ
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: RP
                                                                     
6.1.24 Clean and lubricate the Scrubber rails		 Completed: AQ
6.1.25 Clean and lubricate the Paddle rails		 Completed: AQ
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: RP
6.1.27 Scrub clean the Polish area tub and walls         Completed: RP
6.1.28 Remove all Load and Unload cups and scrub clean             
       with hydrogen peroxide.                           Completed: RP
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: RP
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: RP
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed: RP
6.1.32 Check Carrier clean brushes for defects           Completed: RP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: RP
                                                                    
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: RP
6.1.35 Check chiller fluid resevoir for proper level     Completed: RP
6.1.36 Check the chiller readout for 24 degrees C.       Completed: RP
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: RP
6.1.38 Check the slurry flow alarm.                      Completed: RP
COMMENTS: 
6.1.10 - Check Transport Paddle L/R pressure for 25-35 PSI 
         Applicable for CMP.B1 only.  Engineer informed.
6.1.19 - Found small puddle of DI under load cup 4 area of drip pan.
	 No leak found. Engineer informed.
    
 | 
| 20.84 | WW40 Weekly PM completed. | FABSIX::R_POIRIER |  | Tue Apr 01 1997 01:20 | 105 | 
|  | 
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:3/31/97       TOOL ENTITY:CMP.B2        TECH(S):  Roger Poirier  (RP)
                                                       Bruce Durgin   (BD)
                                                       
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 RP/BD
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 RP/BD
                                                                        
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 RP/BD
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 RP/BD
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 RP/BD
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 RP/BD
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 RP/BD
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 RP/BD
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.0 RP/BD
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A RP/BD
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 RP/BD
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 45 RP/BD
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 RP/BD
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 RP/BD
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 RP/BD
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 RP/BD
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 RP/BD
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 RP/BD
6.1.19 Check Drip Pans for moisture/contamination        Completed:  RP/BD
6.1.20 Check tubing/fittings for fluid leaks             Completed: RP/BD
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: RP/BD
                                                                       
6.1.22 Check stations/components for contamination	 Completed: RP/BD
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 9 RP
                                                                     
6.1.24 Clean and lubricate the Scrubber rails		 Completed: RP/BD
6.1.25 Clean and lubricate the Paddle rails		 Completed: /BD
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: BD
6.1.27 Scrub clean the Polish area tub and walls         Completed: RP
6.1.28 Remove all Load and Unload cups and scrub clean             
       with hydrogen peroxide.                           Completed: RP
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: BD
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: RP/BD
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed: RP
6.1.32 Check Carrier clean brushes for defects           Completed: RP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: RP
                                                                    
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: RP
6.1.35 Check chiller fluid resevoir for proper level     Completed: RP
6.1.36 Check the chiller readout for 24 degrees C.       Completed: RP
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: RP
6.1.38 Check the slurry flow alarm.                      Completed: RP
COMMENTS: 
6.1.10 - Check Transport Paddle L/R pressure for 25-35 PSI 
         Applicable for CMP.B1 only.  Engineer informed.
6.1.19 - Found small puddle of DI under load cup 4 area of drip pan.
	 Couldn't find where leak originated. Engineer informed.
    
 | 
| 20.85 | MONTHLY PM COMPLETED FOR WW41 | SUBPAC::BJUBINVILLE | CMP Equipment Engineering | Sat Apr 12 1997 01:38 | 180 | 
|  | 
                     SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           SPEC# HF60-0172  REV-E 
                        Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev. E 
DATE: 4/11/97 TOOL ENTITY: CMP.B2  TECHNICIAN(S): Brian Jubinville (BJ)
                                                  Leon Shkolnikov (LS)   
6.2.1  Change Peristaltic Pump Lines and check flow     Completed: BJ/LS 
6.2.2  Clean Polish area tub drains for clogs		Completed: BJ/LS 
6.2.3  Check all table belts for defects		Completed: BJ/LS 
6.2.4  Perform Down Force Calibration on all 5 heads   
       to read at +/- 1lbs of 354 lbs.
       NOTE:  The target is 23 lbs. below the actual
       377 lbs. due to the carrier weight minus the
       alignment fixture using the point-to-point
       method as described in the downforce procedure
       in 6.2.4.1 through 6.2.4.13.                     Completed: BJ/LS 
                                                                   
       Down Frc: Head 1 Pre-Adj: 357      Post-adj: 354
                 Head 2 Pre-Adj: 350      Post-adj: 354
                 Head 3 Pre-Adj: 357      Post-adj: 354
                 Head 4 Pre-Adj: 344      Post-adj: 354
                 Head 5 Pre-Adj: 352      Post-adj: 354
6.2.5  Perform Down Force Calibration on Conditioner    Completed: BJ/LS 
       to read +/- .5 lbs of 77lbs.
 
       Actual Down Force Pre-Adj.: 70.2 
       Actual Down Force Post-Adj.: 77
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: 
6.2.7  Check the Load Flipper alignment			Completed: BJ
6.2.8  Check the Unload Flipper alignment		Completed: BJ
								   
6.2.9  Check Elevator alignments			Completed: BJ
								   
6.2.10 Check wafer unload, from Index table to cassette Completed: BJ
								          
6.2.11 Check the +24 Volt power supply for +/- 1V
       of  24V.                Pre: 22.5   Post: 23.8       Tech: BJ/LS 
6.2.12 Check the +15 Volt power supply for +/- 1V
       of 15V.                 Pre: 15.01   Post: 15.01   Tech: BJ
                           
6.2.13 Check the +5 Volt power supply for 4.5 to
       5.5 v.                  Pre: 4.8    Post: 4.8      Tech: BJ
6.2.14 Check Table Rotation Speed for +/- 1.5 of 30RPM  Completed: LS 
 
6.2.15 Check Vacuum Pump Diaphrams			Completed: LS
6.2.16 Replace liquid separator filter element          Completed: LS
6.2.17 Check Vacuum Tank/Pump lines			Completed: LS
6.2.18 Check carrier to Load Cup Position alignments    Completed: BJ/LS 
6.2.19 Check Load Cup Height to carrier alignments      Completed: BJ/LS 
6.2.20  Check the Robot alignments                      Completed: BJ
                                         
6.2.21 Check Muffin Fans for proper operation           Completed: BJ/LS 
Comments: 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 4/11/97  TOOL ENTITY:  CMP.B2  TECHNICIAN(S): Brian Jubinville (BJ)
                                                    Leon Shkolnikov (LS)   
						  
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 BJ
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 BJ
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 26 BJ
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 BJ
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 BJ
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 BJ
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 BJ
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 BJ
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6 BJ
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A BJ
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 BJ
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 BJ
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 BJ
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 BJ
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 BJ
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 BJ
                                 
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 BJ
6.1.19 Check Drip Pans for moisture/contamination        Completed: LS   
6.1.20 Check tubing/fittings for fluid leaks             Completed: LS/BJ 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: LS/BJ 
6.1.22 Check stations/components for contamination	 Completed: LS/BJ     
								    
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 2 BJ
6.1.24 Clean and lubricate the Scrubber rails		 Completed: LS
6.1.25 Clean and lubricate the Paddle rails		 Completed: LS
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: LS
6.1.27 Scrub clean the Polish area tub and walls         Completed: LS/BJ 
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: LS/BJ 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: LS
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: LS/BJ 
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: LS
6.1.32 Check Carrier clean brushes for defects           Completed: LS/BJ 
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: LS/BJ 
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: LS/BJ 
6.1.35 Check chiller fluid resevoir for proper level     Completed: BJ
6.1.36 Check the chiller readout for 24 degrees C.       Completed: BJ
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: LS 
 
6.1.38 Check the slurry flow alarm.                      Completed: LS
Comments:
                                                                    
 | 
| 20.86 | ww42 weekly pm. | FABSIX::L_SHKOLNIKOV |  | Wed Apr 16 1997 00:14 | 102 | 
|  | 
                          CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
                                                                      
DATE:4/15/97       TOOL ENTITY:CMP.B2        TECH(S):  Leon Shkolnikov (ls)
                                                       Dave Whitford   (DW)
                                                       
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 ls   
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 ls   
                                                                        
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 24 DW    
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 DW
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 DW
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 DW
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 DW
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 DW
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.0 DW
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A ls   
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 DW
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 DW
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 52 DW
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 DW
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 DW
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 DW
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 DW
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 DW
6.1.19 Check Drip Pans for moisture/contamination        Completed: ls*
6.1.20 Check tubing/fittings for fluid leaks             Completed: ls   
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: ls   
                                                                       
6.1.22 Check stations/components for contamination	 Completed: ls   
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 9 ls
                                                                     
6.1.24 Clean and lubricate the Scrubber rails		 Completed: ls   
6.1.25 Clean and lubricate the Paddle rails		 Completed: ls 
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: ls
6.1.27 Scrub clean the Polish area tub and walls         Completed: ls
6.1.28 Remove all Load and Unload cups and scrub clean             
       with hydrogen peroxide.                           Completed: ls
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: ls
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: ls   
6.1.31 Remove and clean the Vacuum system filter                     
       element and replaced as needed.                   Completed: ls
6.1.32 Check Carrier clean brushes for defects           Completed: ls
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: ls
                                                                    
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: ls
6.1.35 Check chiller fluid resevoir for proper level     Completed: ls
6.1.36 Check the chiller readout for 24 degrees C.       Completed: ls
6.1.37 Check the positioning and functionality of the                
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: ls
6.1.38 Check the slurry flow alarm.                      Completed: ls
COMMENTS: 
*6.1.19 - Found small puddle of DI under load cup 4 area of drip pan.
	 Couldn't find where leak originated. Engineer informed.
    
 | 
| 20.87 | WW43 weekly pm complete | FABSIX::O_WHITFORD | Lead, follow or step aside. | Thu Apr 24 1997 13:16 | 104 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 4/24/97        TOOL ENTITY: CMP.B2     TECHNICIAN(S): Dave Whitford (DW)
                                                            John Poirier  (JP)
START TIME: 10:30       COMPLETED TIME: 12:30
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 DW
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 DW
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 22 DW
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 DW
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 DW
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 DW
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 DW
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 DW
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.2 DW 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A DW
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 DW
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 DW
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 DW
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 DW
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 20 DW
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 DW
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 DW
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 DW
6.1.19 Check Drip Pans for moisture/contamination        Completed: JP  
6.1.20 Check tubing/fittings for fluid leaks             Completed: JP 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: JP 
6.1.22 Check stations/components for contamination	 Completed: JP 
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:  9 JP
6.1.24 Clean and lubricate the Scrubber rails		 Completed: JP
6.1.25 Clean and lubricate the Paddle rails		 Completed: JP
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: DW
6.1.27 Scrub clean the Polish area tub and walls         Completed: DW
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: DW
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: JP
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: JP
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: JP
6.1.32 Check Carrier clean brushes for defects           Completed: JP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: JP
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: JP
6.1.35 Check chiller fluid resevoir for proper level     Completed: JP
6.1.36 Check the chiller readout for 24 degrees C.       Completed: JP
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: DW 
6.1.38 Check the slurry flow alarm.                      Completed: JP  
Comments: Lost Infranor for ROTATION, ARM 5 when tool was powered up.
Powered down to replace and then ROTATION ARM 2 appeared dead. While
signing on to order replacement, came b ack and ROTATION ARM 2 now
indicates o.k. Passed initialization. ???? 
 | 
| 20.88 | WW 44 WEEKLY COMPLETED FOR B2 | FABSIX::J_SWENSON |  | Wed Apr 30 1997 19:35 | 99 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE:4/30/97      TOOL ENTITY:CMP.B2       TECHNICIAN(S):MIKE STANDING
START TIME:1540   COMPLETED TIME:1810
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed:MS
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed:MS
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed:MS
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed:MS
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed:MS
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed:MS
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed:MS
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed:MS
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed:MS
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed:MS
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed:MS
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed:MS
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed:MS
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed:MS
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed:MS
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed:MS
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed:MS
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed:MS
6.1.19 Check Drip Pans for moisture/contamination        Completed:MS  
6.1.20 Check tubing/fittings for fluid leaks             Completed:MS  
6.1.21 Check tubing/fittings for pneumatic leaks         Completed:MS  
6.1.22 Check stations/components for contamination	 Completed:MS  
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:MS
6.1.24 Clean and lubricate the Scrubber rails		 Completed:MS 
6.1.25 Clean and lubricate the Paddle rails		 Completed:MS 
6.1.26 Remove and clean conditioning Wheel and Housing   Completed:MS
6.1.27 Scrub clean the Polish area tub and walls         Completed:MS
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed:MS
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed:MS
6.1.30 Check slurry pump hoses and connectors for leaks  Completed:MS 
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed:MS
6.1.32 Check Carrier clean brushes for defects           Completed:MS
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed:MS
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed:MS
6.1.35 Check chiller fluid resevoir for proper level     Completed:MS 
6.1.36 Check the chiller readout for 24 degrees C.       Completed:MS
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:MS  
6.1.38 Check the slurry flow alarm.                      Completed:MS  
Comments:
 | 
| 20.89 | ww45 weekly pm check sheet | ASDG::POIRIER |  | Sat May 10 1997 18:53 | 102 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 5/10/97   TOOL ENTITY: CMP.B2  TECHNICIAN(S): John Poirier (JP)
                                                    Mike Standing (MS)
START TIME: 5:30 P.M.       COMPLETED TIME: 6:50 P.M.
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 JP
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 JP
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 30 JP
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 JP
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 19 JP
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 JP
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 35 JP
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 JP
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.2 JP 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A  *
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 18 JP
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 JP
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 50 JP
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 JP
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 JP
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 JP
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 JP
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 JP
6.1.19 Check Drip Pans for moisture/contamination        Completed:    JP
6.1.20 Check tubing/fittings for fluid leaks             Completed:    JP
6.1.21 Check tubing/fittings for pneumatic leaks         Completed:    JP
6.1.22 Check stations/components for contamination	 Completed:    JP
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:  4 JP
6.1.24 Clean and lubricate the Scrubber rails		 Completed:    JP
6.1.25 Clean and lubricate the Paddle rails		 Completed:    JP
6.1.26 Remove and clean conditioning Wheel and Housing   Completed:    JP
6.1.27 Scrub clean the Polish area tub and walls         Completed:    JP
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed:    JP
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed:    JP
6.1.30 Check slurry pump hoses and connectors for leaks  Completed:    JP
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed:    MS
6.1.32 Check Carrier clean brushes for defects           Completed:    JP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed:    JP
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed:    JP
6.1.35 Check chiller fluid resevoir for proper level     Completed:    JP
6.1.36 Check the chiller readout for 24 degrees C.       Completed:    JP
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:    JP
6.1.38 Check the slurry flow alarm.                      Completed:    MS
Comments: 6.1.10 APPLIES TO CMP.B1 ONLY.
 | 
| 20.90 | Monthly PM completed | FABSIX::R_POIRIER |  | Wed May 14 1997 10:29 | 189 | 
|  | 
                     SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                           SPEC# HF60-0172  REV-E 
                        Speedfam Corp. CMP-V Planarizer
                Monthly Preventative Maintenance Check Sheet, Rev. E 
DATE: 5/12/97 TOOL ENTITY: CMP.B2  TECHNICIAN(S): Roger Poirier (RP)
                                                  Bruce Durgin (BD)   
6.2.1  Change Peristaltic Pump Lines and check flow     Completed: BD/RP
6.2.2  Clean Polish area tub drains for clogs		Completed: RP/BD
6.2.3  Check all table belts for defects		Completed: RP/BD
6.2.4  Perform Down Force Calibration on all 5 heads   
       to read at +/- 1lbs of 354 lbs.
       NOTE:  The target is 23 lbs. below the actual
       377 lbs. due to the carrier weight minus the
       alignment fixture using the point-to-point
       method as described in the downforce procedure
       in 6.2.4.1 through 6.2.4.13.                     Completed: RP
                                                                   
       Down Frc: Head 1 Pre-Adj: 358      Post-adj: 355
                 Head 2 Pre-Adj: 351      Post-adj: 354
                 Head 3 Pre-Adj: 356      Post-adj: 355
                 Head 4 Pre-Adj: 348      Post-adj: 355
                 Head 5 Pre-Adj: 351      Post-adj: 354
6.2.5  Perform Down Force Calibration on Conditioner    Completed: RP
       to read +/- .5 lbs of 77lbs.
 
       Actual Down Force Pre-Adj.: 72.1 
       Actual Down Force Post-Adj.: 77
6.2.6  Check Scrubber Brushes for contaminates/defects	Completed: RP/BD
6.2.7  Check the Load Flipper alignment			Completed: RP/BD
6.2.8  Check the Unload Flipper alignment		Completed: RP/BD
								   
6.2.9  Check Elevator alignments			Completed: RP
								   
6.2.10 Check wafer unload, from Index table to cassette Completed: RP
								          
6.2.11 Check the +24 Volt power supply for +/- 1V
       of  24V.                Pre: 23.8   Post: 23.8       Tech: RP
6.2.12 Check the +15 Volt power supply for +/- 1V
       of 15V.                 Pre: 15.02   Post: 15.01   Tech: RP
                           
6.2.13 Check the +5 Volt power supply for 4.5 to
       5.5 v.                  Pre: 4.90    Post: 4.90      Tech: RP 
6.2.14 Check Table Rotation Speed for +/- 1.5 of 30RPM  Completed: RP
 
6.2.15 Check Vacuum Pump Diaphrams			Completed: RP/BD
6.2.16 Replace liquid separator filter element          Completed: BD/BD
6.2.17 Check Vacuum Tank/Pump lines			Completed: RP/BD
6.2.18 Check carrier to Load Cup Position alignments    Completed: RP/BD
6.2.19 Check Load Cup Height to carrier alignments      Completed: RP/BD
6.2.20  Check the Robot alignments                      Completed: RP/BD
                                         
6.2.21 Check Muffin Fans for proper operation           Completed: RP
Comments: 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 5/12/97  TOOL ENTITY:  CMP.B2  TECHNICIAN(S): Rgoer Poirier (RP)
                                                    Bruce Durgin (BD)   
						  
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 RP/BD 
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 RP/BD
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 25 RP/BD
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 RP/BD
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 20 RP/BD
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 RP/BD
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 RP/BD
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 RP/BD
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.5 RP/BD
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A RP
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20 RP/BD
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 RP/BD
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 52 RP/BD
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 RP/BD 
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 RP/BD
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 RP/BD
                                 
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 RP/BD
6.1.19 Check Drip Pans for moisture/contamination        Completed: RP/BD *
6.1.20 Check tubing/fittings for fluid leaks             Completed: RP/BD
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: RP/BD
6.1.22 Check stations/components for contamination	 Completed: RP/BD
								    
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 2 RP 
6.1.24 Clean and lubricate the Scrubber rails		 Completed: BD
6.1.25 Clean and lubricate the Paddle rails		 Completed: BD
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: RP
6.1.27 Scrub clean the Polish area tub and walls         Completed: BD
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: BD
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: BD
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: RP
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: BD
6.1.32 Check Carrier clean brushes for defects           Completed: RP
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: RP/BD
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: BD
6.1.35 Check chiller fluid resevoir for proper level     Completed: BD
6.1.36 Check the chiller readout for 24 degrees C.       Completed: RP
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: RP/BD
 
6.1.38 Check the slurry flow alarm.                      Completed: RP/BD
Comments:
	6.1.10 - Check Transport Paddle L/R pressure for 25-35 PSI
        	 Applicable for CMP.B1 only.  Engineer informed.
	6.1.19 - Found small puddle of DI under load cup 4 area of drip pan.
        	 No leak found. Engineer informed.
       
	Note:	Found Left side Bulkhead cable #3 had frayed outer shielding.
		No damage to inner shield or wires noted. E.E informed.
                      
 | 
| 20.91 | ww47 weekly p.m. completed / pads changed | FABSIX::R_GEE |  | Sun May 18 1997 09:23 | 103 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 5/18/97   TOOL ENTITY: CMP.B2  TECHNICIAN(S): Jim Sadin (JS)
                                                    Bob Gee (BG)
						    Dave Whitford (DW)
START TIME: 8:30 A.M.       COMPLETED TIME: 9:45 A.M.
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 80 BG
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 55 BG
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 22 BG
6.1.4  Check Load Cup pressure for 40-50 PSI		 Completed: 40 BG
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 19 BG
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35 BG
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30 BG
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 50 BG
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6.2 BG 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A  *
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 18 BG
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50 BG
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 52 BG
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 25 BG
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 25 BG
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 20 BG
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45 BG
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80 BG
6.1.19 Check Drip Pans for moisture/contamination        Completed:    BG
6.1.20 Check tubing/fittings for fluid leaks             Completed:    BG
6.1.21 Check tubing/fittings for pneumatic leaks         Completed:    BG
6.1.22 Check stations/components for contamination	 Completed:    BG
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed:  6 BG
6.1.24 Clean and lubricate the Scrubber rails		 Completed:    DW
6.1.25 Clean and lubricate the Paddle rails		 Completed:    DW
6.1.26 Remove and clean conditioning Wheel and Housing   Completed:    DW/JS
6.1.27 Scrub clean the Polish area tub and walls         Completed:  DW/JS/BG
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed:  DW/JS/BG
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed:  DW/JS/BG
6.1.30 Check slurry pump hoses and connectors for leaks  Completed:    JS
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed:    BG
6.1.32 Check Carrier clean brushes for defects           Completed:    JS
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: DW/JS/BG
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: DW/JS/BG
6.1.35 Check chiller fluid resevoir for proper level     Completed:    DW   
6.1.36 Check the chiller readout for 24 degrees C.       Completed:    DW
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed:  DW/JS/BG
6.1.38 Check the slurry flow alarm.                      Completed:  DW/JS/BG
Comments: 6.1.10 APPLIES TO CMP.B1 ONLY.
	Changed both primary and secondary pads due to high wafer count.
 | 
| 20.92 | WW48 weekly pm completed. | FABSIX::J_SADIN | Freedom isn't free. | Tue May 27 1997 09:22 | 101 | 
|  | 
                      SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                             SPEC# HF60-0172  REV-E  
                      
                       Speedfam Corp. CMP-V Planarizer
                Weekly Preventative Maintenance Check Sheet, Rev. E
DATE: 5/25/97    TOOL ENTITY: CMP.B2    TECHNICIAN(S):  James Sadin    (js)
                                                        Bob Gee        (bg)
                        `                               Timothy Landry (tl)
                                                        Brendan Finn   (bf)
6.1.1  Check CDA pressure inside tool for 80-90 PSI	 Completed: 85 bg 
6.1.2  Check N2 pressure inside tool for 55-65 PSI       Completed: 57 bg
6.1.3  Check incoming DI Water pressure for 20-30 PSI    Completed: 28 bg
6.1.4  Check Load Cup pressure for 40-50 PSI	       	 Completed: 45js/tl
6.1.5  Check Pad Condition Balance pressure 10-20 PSI	 Completed: 15js/tl
6.1.6  Check Pad Conditioner Up pressure for 30-40 PSI	 Completed: 35js/tl
6.1.7  Check Carrier Up pressure for 25-35 PSI		 Completed: 30js/tl
6.1.8  Check Miscellaneous pressure for 40-50 PSI        Completed: 45js/tl
6.1.9  Check Head Balance pressure for 6-6.5 PSI         Completed: 6 js/tl 
6.1.10 Check Transport Paddle L/R pressure for 25-35 PSI Completed: N/A 
       (Applicable for CMP.B1 only)
6.1.11 Check Transport Paddle U/D pressure for 10-20 PSI Completed: 20js/tl
6.1.12 Check Open Load Flipper pressure for 45-55 PSI	 Completed: 50bg/bf
6.1.13 Check Open Unload Flipper pressure for 50-60 PSI	 Completed: 55bg/bf
6.1.14 Check Vacuum Tank Blowout pressure for 15-30 PSI  Completed: 28bg/bf
6.1.15 Check Wafer Scrub Down pressure for 20-30 PSI	 Completed: 30js/tl
6.1.16 Check Alignment Fixture pressure for 15-25 PSI    Completed: 25js/tl
6.1.17 Check Scrubber In/Out pressure for 45-55 PSI	 Completed: 45js/tl
6.1.18 Check MHTA pressure for 75-85 PSI	         Completed: 80js/tl
6.1.19 Check Drip Pans for moisture/contamination        Completed: bf 
6.1.20 Check tubing/fittings for fluid leaks             Completed: bg 
6.1.21 Check tubing/fittings for pneumatic leaks         Completed: bg
6.1.22 Check stations/components for contamination	 Completed: tl/js/bf/bg 
6.1.23 Check incoming Chilled Water pressure <10 PSI	 Completed: 8 js 
6.1.24 Clean and lubricate the Scrubber rails		 Completed: bg
6.1.25 Clean and lubricate the Paddle rails		 Completed: bf
6.1.26 Remove and clean conditioning Wheel and Housing   Completed: tl
                                                         
6.1.27 Scrub clean the Polish area tub and walls         Completed: bg 
6.1.28 Remove all Load and Unload cups and scrub clean    
       with hydrogen peroxide.                           Completed: tl/js/bf/bg 
6.1.29 Wipe the Load area, Mapper and Aligner w/ISO      Completed: bg 
6.1.30 Check slurry pump hoses and connectors for leaks  Completed: js
6.1.31 Remove and clean the Vacuum system filter          
       element and replaced as needed.                   Completed: tl 
6.1.32 Check Carrier clean brushes for defects           Completed: bf
       (On CMP.B1, rotate position)
6.1.33 Wipe the MHTA and covers with Isopropyl           Completed: bf/tl
6.1.34 Wipe the Process Area plexiglas doors w/Iso       Completed: js
6.1.35 Check chiller fluid resevoir for proper level     Completed: js/tl
6.1.36 Check the chiller readout for 24 degrees C.       Completed: js
6.1.37 Check the positioning and functionality of the
       wafer detect sensors.  Use the procedure in
       step 6.1.37.4 to check sensors without having to
       make any adjustments.                             Completed: js/tl/bf 
6.1.38 Check the slurry flow alarm.                      Completed: tl 
Comments:  6.1.10 - applicable to CMP.B1 only.  
 | 
| 20.93 | CMP.B2 SHUTDOWN AND STARTUP CHECKSHEETS | FABSIX::J_SADIN | Freedom isn't free. | Tue May 27 1997 09:51 | 50 | 
|  | --------------------------------------------------------------------------------
        
SPEC# HF60-0172  REV-E       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
				CMP.B2
                        CMP.B SHUT DOWN CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
								 INIT / DATE
1) SCRUB SIDES OF CARRIERS				      RP,AQ,BD/5-26-97
2) RUN CARRIER BLOW OFF FOR 30 SECONDS			      RP,AQ,BD/5-26-97
3) REMOVE ALL CARRIERS					      RP,AQ,BD/5-26-97
4) PLACE WIPES UNDER CARRIER FILMS AND LAY CARRIERS DI TANK   RP,AQ,BD/5-26-97
5) IF POWER TO SLURRY SYSTEM IS GOING TO BE LOST, CONTACT 
   ASHLAND CHEMICAL AND HAVE SLURRY SYSTEM PURGED AND CHARGED 
   WITH DI WATER.					      RP,AQ,BD/5-26-97
6) CLEAN ENTIRE SYSTEM OF DRIED SLURRY 			      RP,AQ,BD/5-26-97
7) REMOVE CONDITIONER AND CLEAN				      RP,AQ,BD/5-26-97
8) CYCLE/RINSE ALL DI FUNCTIONS: SPRAY NOZZLES, SLURRY PUMPS,
   CONDITIONER RINSE, ELEVATOR TANKS.			      RP,AQ,BD/5-26-97
9) SHUT OFF DI BEHIND SYSTEM (ROTATE 3W VLV TO FULL RETURN)   RP,AQ,BD/5-26-97
10) DRAIN ELEVATOR AND CONDITIONER TUBE			      RP,AQ,BD/5-26-97
11) REMOVE PADS, AND CLEAN AND DRY TABLES		      RP,AQ,BD/5-26-97
12) REMOVE SCRUBBER BRUSHES AND SOAK IN DI		      RP,AQ,BD/5-26-97
13) DRY ENTIRE SYSTEM OF ANY STANDING WATER		      RP,AQ,BD/5-26-97
14) POWER DOWN SYSTEM.
SPEC# HF60-0172  REV-D       SPEEDFAM CMP-V PREVENTIVE MAINTENANCE
                        CMP.B START UP CHECK SHEET
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
                                                                 INIT / DATE
1) TURN ON DI WATER (ROTATE 3W VLV TO FULLY TO POLISHER.	_js/tl/05/27_
2) POWER ON SYSTEM.					        _js/tl/05/27_
3) CYCLE/RUN ALL DI FUNCTIONS FOR 15 MINUTES			_js/tl/5/27__
4) WIPE DOWN SYSTEM CLEAN ALL DRIED SLURRY	                _js/tl/5/27__
5) DRY TABLES, INSTALL PADS					_js/tl/5/27__
6) INSTALL SCRUBBER BRUSHES					_js/tl/5/27__
7) INSTALL CONDITIONER						_js/tl/5/27__
8) INSTALL CARRIERS						_js/tl/5/27__
9) RUN WET IDLE PROGRAM FOR 15 MIN. (ENOUGH TO CLEAN CARRIERS)  _js/tl/5/27__
10) IF SLURRY SYSTEM WAS SHUT DOWN, CONTACT ASHLAND CHEMICAL,
    REQUEST DI TO BE PURGE FROM SLURRY SYSTEM AND CHARGED WITH 
    SLURRY AND REQUEST A NEW SLURRY FILTER BE INSTALLED.	_js/tl/5/27__
11) CALIBRATE SLURRY FLOW					_NA__________
12) PUT IN WET IDLE AND TURN OVER TO MFG FOR MQC		_js/tl/5/27__
 |